14:53 May 26, 2013  

Hindustan Construction Company Ltd

HSL Code: HINCON   |   BSE Code: 500185  |   NSE Symbol: HCC  |   ISIN: INE549A01026
13.39
-0.16(-1.18%)
24 May 2013 | 15:45
Prev Close (Rs.)
13.55
Open (Rs.)
14.00
High (Rs.)
14.00
Low (Rs.)
13.31
Volume
1,77,049
Week Avg. Volume
2,34,933
52Wk High - Low Range
13.26
22.15
 
 
HINDUSTAN CONSTRUCTION COMPANY LIMITED

ANNUAL REPORT 2011-2012

DIRECTOR`S REPORT

To,
The Members of
Hindustan Construction Co. Ltd.

1. Report

Your Directors are pleased to present the 86th Annual Report together  with 
the Audited Accounts for the year ended March 31, 2012.

2. Financial Highlights

Particulars                             Year ended              Year ended
                                    March 31, 2012          March 31, 2011
                                         Rs. crore               Rs. crore

Turnover                                   4002.75                 4143.97

Profit before Interest, 
Depreciation, Exceptional                   439.80                  540.89
Items and Tax

Less: Interest                  543.16                  329.04

Depreciation                    162.10                  152.69

Exceptional Items               166.32      871.58           -      481.73

Add: Other Income                           122.83                   43.91

Add/Less: Exchange 
Gain/(Loss)                                 (9.53)                    8.60

Profit/(Loss) 
before Tax                                (318.48)                  111.67

Less:  Deferred Tax 
Charge/(Credit)                            (96.23)                   40.67

Profit/(Loss) after Tax                   (222.25)                   71.00

Add: Balance brought 
forward from last year                      347.83                  319.62

Transfer from Debenture 
Redemption Reserve                           16.67                    4.16

Amount available for 
Appropriation                               142.25                  394.78

Less: Appropriations

Dividend                             -                   24.26

Tax on Dividend                      -                    3.94

Debenture Redemption 
Reserve                          16.25                    8.75

Transfer to General 
Reserve                              -       16.25       10.00       46.95

Balance carried to 
Balance Sheet                               126.00                  347.83

3. Dividend

In  view  of the losses incurred by the Company, your  Directors  have  not 
recommended any dividend for the financial year ended March 31, 2012.

4. Operations

The turnover of the Company at  Rs. 4003 crore has shown a decrease of 3.4% 
as  compared to  Rs. 4144 crore for the previous year. The loss before  tax 
is   Rs. 318.5 crore (including exceptional item of  Rs. 166.32  crore)  as 
compared to a profit of  Rs. 111.7 crore for the previous year.

The lower turnover and operating margins in an environment of high interest 
costs has put severe pressure on the Company`s profitability. Non  payments 
of  awarded claims in arbitrations added to the liquidity problem and  debt 
servicing  ability  and  increased  interest  costs  further.  The  Company 
approached  lender  Bankers  with  a  refinancing  proposal  for  bilateral 
refinancing  of  the  loans with larger  tenure.  However  consensus  among 
Bankers  could  not be reached. Consequently, the  Company  approached  the 
leading  bankers and they have referred their total debt to the Company  of 
around  Rs. 3300 crore to the Corporate Debt Restructuring (CDR) Cell.  The 
CDR Empowered Group has formally admitted the proposal for restructuring on 
March  29, 2012 by a super majority of lenders. Under the regulatory  frame 
work  of  the  Reserve  Bank of India (RBI), the CDR  forum  caters  to  an 
official  platform  for both the creditors and borrowers  to  amicably  and 
collectively evolve policies for working out debt restructuring plans.  The 
broad  contours  of this restructuring exercise involves  restructuring  of 
debt in terms of payback period, deferring certain interests on term loans, 
concessional  rate of interest and provision of further need based  working 
capital  and  loans  for capex. This debt restructuring  will  provide  the 
Company  with breathing space to work on improving operational margins  and 
securing  a  larger order book to improve turnover in future  years.  Apart 
from  focusing on cost cutting measures and cost effective  execution,  the 
Company  will also focus on sale of non-core assets to improve its  balance 
sheet position.

Your Directors are pleased to inform that during the year under review, the 
Company has secured the following major contracts.

* Limbdi Branch Canal Project, Gujarat 
Contract Value:  Rs. 299 crore

* Tehri Pumped Storage Project, Uttarakhand 
Contract Value:  Rs. 1843 crore

* Superstructure of Bogibeel Rail-cum-Road Bridge, Assam 
Contract Value:  Rs. 987 crore

*  Swarnim  Gujarat Saurashtra-Kutch Water Grid Programme. Package  NC  31, 
Gujarat
Contract Value:  Rs. 289 crore

* Single Line Tunnel No. 10 between Jiribam and Tupul, Manipur
Contract Value:  Rs. 162 crore

The  total  balance  value of works on hand as on March 31,  2012  is   Rs. 
15,336 crore.

Decisions  are  awaited from various clients for tenders submitted  by  the 
Company  (directly or in JV) for 15 projects amounting to about  Rs.  7,745 
crore. Tenders for various packages for 32 projects worth about  Rs. 27,485 
crore are expected to be submitted in the near future. The Company has also 
submitted  prequalification  bids  for 12 projects worth  over   Rs.  7,588 
crore,  which are currently under evaluation. The Company is  confident  of 
securing a sizeable share of these new projects. 

Operations of Subsidiaries 

(i) Lavasa Corporation Ltd. - Integrated Urban Development & Management 

a) Operations

Lavasa is a planned hill city being developed by Lavasa Corporation Ltd., a 
subsidiary Company. Located in the western region of India, the city is  an 
hour drive from Pune and three hours drive from Mumbai. It is one fifth the 
size  of  Greater  Mumbai Municipal limits. The master plan  of  Lavasa  is 
developed  by  internationally  renowned design consultant  HOK,  USA.  The 
master  plan,  recipient  of many international awards,  is  based  on  the 
principles  of  New  Urbanism  that  brings  together  all  the  components 
essential  to  daily  life  in a more organized  manner.  Lavasa  has  many 
pioneering initiatives to its credit - technology leadership, e-Governance, 
city developed using Geographical Information System (GIS), etc. Lavasa  is 
planned for a permanent population of around 3 lakh residents and a tourist 
inflow that is envisaged at 20 lakh per annum. It aims to provide a perfect 
work-life   balance   with  an  unique  combination   of   technology   and 
infrastructure  advancements. The city will have a 365 day economy  with  a 
host  of  non  polluting industries being the main  economic  driver  which 
includes R&D and training centres, IT and biotech industry, KPOs and  those 
related to art, fashion and animation.

In  terms of awards and accolades, the thought leadership  platform  Lavasa 
Future  Cities won the Silver Medal at the Olive Crown Awards for  creative 
excellence in `Green` communication. This award recognizes pioneering  work 
in  communicating  sustainability  and has been instituted  by  the  Indian 
chapter  of the International Advertising Association (IAA) with  Knowledge 
Partner  TERI  (The Energy Resource Institute). The Limca Book  of  Records 
also  acknowledged  the Lavasa Women`s Drive 2011 (and  2010)  as  `India`s 
Biggest All-Women Car Drive`.

On  the  hospitality  front,  the  hospitality  units  which  are   already 
operational  are: Lavasa International Convention Centre managed by  ACCOR, 
Mercure  Lavasa, Fortune Select Dasve, Ekaant - The Retreat,  Dasvino  Town 
and Country Club and Waterfront Shaw Serviced Apartments. Other than  this, 
Radisson,  ITC  Luxury  Collection, Choice  Hotel,  J.  Vohra  Hospitality, 
Novotel  by Accor, Pullamn by Accor, Hilton, Ramada, Oakwood,  Two  Langham 
properties,  Holiday Inn, Days Inn Hotel are already tied up and many  more 
are to follow in quick succession giving Lavasa a new hotel property  every 
6 months.

An equal amount of progress has been made in the education space. `Christel 
House  School, Lavasa` entered into its second year of operations with  209 
students.  After  the success of the first year, in the year  2011-12,  the 
phase  -  II  of `Christel House Lavasa`  was  launched.  `Ecole  Hoteliere 
Lavasa`  started its third batch and received academic  certification  from 
Ecole  hoteliere  de  Lausanne to conduct the Masters  Programmes  and  for 
offering  and conducting degrees from IGNOU. Next on the agenda this  year, 
is Lavasa Musoorie International School powered by Educomp.Other than this, 
Ryan  International for performing arts, Birla Edutech (by Yash  Birla)  IB 
school,  Gems  International  IB  school,  Management  Institute  by  Bodhi 
Education,  Euro Kids with a primary and pre-primary school, The  Institute 
of  International  Business  Relations Germany, NSHM  Knowledge  Campus  of 
Kolkata,  Symbiosis-Pune and Christ University-Bangalore are also  tied  up 
for setting up their campuses.

Professional and Executive Education has also taken off in Lavasa in a  big 
way with Car Design Workshop by Chris Bangle (Scuola Politecnica di Design) 
the  world  renowned  school of design and communication  based  in  Milan, 
Security Awareness Workshop by Max Security (Israeli Security experts)  and 
Massachusetts  Institute  of  Technology who  have  conducted  their  pilot 
program based on Airport and Airline Systems, Planning and Management. This 
has prepared a platform for them to conduct similar programmes at Lavasa in 
the future.

On  the  retail front, American Diner, Granma`s  Bakery,  Brewberry`s  Cafe 
Memories,  Baskin  & Robbins Kiosk, Tabakh, Oriental Octopus,  Amul  Dairy, 
Chor  Bizarre,  Subway,  Hungry hippo, Krazy Koala  Kiosk,  Twisted  Turkey 
Kiosk, Fruity bat, Pizzavala, Natural Ice Cream, Bizarre Baracuda, Design & 
Build Store - Home Town are already operational.

Positive sales trend continued throughout the year, with the Company giving 
possession  to  150+ residential units in Dasve. Residential sales  of  the 
first  town  Dasve have almost been completed. There have  also  been  many 
enquiries  for  further residential units in Lavasa. Sales for  the  second 
town  Mugaon  was  launched on the occasion of Gudi Padwa  in  March  2012. 
Almost  75% of the inventory has been sold out within just a  fortnight  of 
the launch. It is also heartening to know that there has been less than  1% 
cancellation requests from customers inspite of the Ministry of Environment 
and  Forest  (MoEF) status quo. The current database of enquiries  for  the 
purchase  of  apartments and villas exceeded almost eighty  thousand  which 
indicates a healthy demand.

Institutional  sales and commercial tie ups have also made progress with  a 
number of MoUs being signed. Land sale has been made to State Bank of India 

who  plan to set up a retail bank and a training centre cum guest house  at 
Dasve.  Development  of  an integrated Corporate  Training  Centre  with  a 
residential  component at Mugaon is also being planned by a consortium  led 
by the Giria Investment Corporation, Bengaluru. The Art of Living centre is 
also  slated  to  open at Mugaon. Sales are also fast  picking  up  in  our 
commercial  office spaces ventures - 247 Business Square and  247  Business 
Avenue  at  Lavasa. These are just initial steps towards a 365  day  -  247 
economy that Lavasa is planning to accomplish. In the next year, the target 
is  for  many such industries including IT&ITES,  Biotechnology,  Knowledge 
Parks,  R&D  centres  and Corporate Training centres  to  enable  permanent 
residents to move in.

On  the tourism front, X-Thrill adventure academy, Water Sports, Noes  park 
(games  Arcade),  Nature trail, Train on wheels, Kids  play  Area,  movies, 
parks & gardens are already operational. Other than this, Space theme  park 
(edutainment),  Tennis  Australia, Manchester City Football Club  are  also 
already tied up.

Lavasa  is  also tying up with I Dream to create all  Lavasa  tourism  plan 
including a Historical theme park. This project is being spearheaded by Mr. 
Shirpal  Morakhia, businessman who created Sharekhan. Lavasa is also  tying 
up  with  Engage  Plus,  a  New  Zealand  Company,  for  adventure   sports 
activities, to give adventure experience at Dasve and nearby areas.

Events  continued to be a key focal point and the year saw a  multitude  of 
events that increased the salience of the brand and helped engage with  the 
consumer on-ground. The fourth edition of the signature brand event  Lavasa 
Women`s  Drive  was  held on February 26, 2012. The  event  which  captures 
multiple  aspects - fun, adventure and spirit of the Indian woman  combined 
with  her passion for social causes was flagged off from Mumbai  and  Pune. 
This  year,  Lavasa Women`s Drive also launched the `Women in  the  Driving 
Seat`  awards  where women achievers who had made an impact and  created  a 
benchmark  were  applauded in various fields. These  included  Vidya  Balan 
(Cinema),  Dr. Swati Piramal (Corporate), Dr. Firuza  Parekh  (Healthcare), 
Ekta   Kapoor  (Television),  Tina  Tahiliani  (Fashion),  Shaheen   Mistry 
(Education), Abha Narain Lambah (Community Development), Neela Satyanarayan 
(Administration) and Devieka Bhojwani (Cancer Awareness).

Lavasa  was  the destination partner for the Pantaloons Femina  Miss  India 
(PFMI) pageant for the fourth year in succession. Residential sales of  the 
second  town at Mugaon was launched in the presence of the PFMI  finalists. 
On  this occassion, handover of possession of the residences built  at  the 
first  town  Dasve  to the 100th and 101st apartment owner  has  also  been 
accomplished.

Lavasa  has  collaborated with technology leaders like  Wipro  Limited  and 
Cisco  Systems to plan, implement and manage Information and  Communication 
Technology   (ICT)  services  across  Lavasa  Hill  City.   The   strategic 
partnership  is  intended to focus on providing  integrated  and  effective 
solutions  for  enhancing technology leadership within the hill  city.  The 
Company founded as a result of this venture is named as `My City Technology 
Limited`. This venture is currently deploying a futuristic telecom  network 
infrastructure  to  offer  its  residents  and  visitors  a  life  changing 
technology experience.

Lavasa  now has a new post office, police station, a public safety  centre, 
citizen  call  centre, a hospital managed by Apollo, banks (Union  Bank  of 
India,  State Bank of India), a petrol station, pharmacy, STP, WTP,  rental 
housing,  an  arcade and transit system. In the months ahead it  will  open 
grocery and additional retail shops.

The  city`s  drinking water is fit for consumption straight  from  the  tap 
without the need for filtration; its sewerage is treated to almost drinking 
water  standards before being reused for irrigation and  other  non-potable 
purposes; its power distribution grid is nearly 99% reliable and the  young 
city  is already on the cutting edge of urban environmental  sustainability 
initiatives. The Company plans to

have  its  e-Governance portal and a citizen call centre  to  maintain  its 
focus  on  the needs of residents and visitors, and it has  already  opened 
parks and play areas to the public.

Lavasa continued its focus on branding and communication activities through 
2011-12.

Importantly,Lavasa  was granted Environmental Clearance by the Ministry  of 
Environment  & Forests (MoEF) for the first phase of 2000 hectares (Ha)  in 
November 2011. A large scale PR exercise across media, i.e., print, TV  and 
online  was  undertaken  welcoming the news. Social Media  and  the  Lavasa 
website  disseminate  related information and for addressing queries  as  a 
part  of the exercise. Media engagement and relationship building  exercise 
continued  throughout  the pre-clearance to post-clearance  period.  A  new 
brand  campaign  At Work" was released in 2012. This was  to  reassure  the 
general public at large that developmental work has begun at Lavasa.

Lavasa City Guide - a one - stop source on all information on Lavasa and  a 
new  3D  walkthrough film - `Mugaon - A Virtual Tour` was  created.  A  new 
property  `Lavasa Holidays`, to promote tourism at Lavasa was launched.  An 

engagement program called Brand Conversations was conceptualized which will 
comprise  of informal conversations with the employees across  the  various 
departments  on  how  brand  principles  should  be  applied  to  day-today 
functioning.

Digital  and  social  media  was being  extensively  used  for  information 
dissemination  and creating conversations on a number of platforms  on  the 
web   including  travel,  tourism  and  urban  management  portals.   These 
engagement  initiatives  saw  an increase in the fan  base  of  the  Lavasa 
Community page on Facebook to almost 90,000 fans.

b) Status update on Environment Clearance from Ministry of Environment  and 
Forests (MoEF)

On  November  25,  2010,  Ministry  of  Environment  &  Forests   ("MoEF"), 
Government  of  India  issued  show cause notice under  Section  5  of  the 
Environment  Protection  Act, 1986 to Lavasa  Corporation  Limited  ("LCL") 
alleging violations of the Environmental Impact Assessment notifications of 
1994  as amended in 2004 and superseded in 2006 ("EIA Notifications").  The 
said notice directed LCL to show cause within 15 days of the receipt of the 
said notice as to why the alleged unauthorized structures at Lavasa site be 
not  removed in entirety and pending the decision on show cause  notice  by 
MoEF,  it directed LCL to maintain status-quo ante for construction  and/or 
development.

LCL  has  filed Writ Petition No. 9448 of 2010 against  the  impugned  show 
cause  notice in the Bombay High Court seeking inter alia, quashing of  the 
said  show cause notice and stay on status quo pending the decision on  the 
Writ  Petition. On December 7, 2010, the Counsel for MoEF made a  statement 
in  the  Bombay High Court that the words "status quo ante" in  the  MoEF`s 
show  cause notice dated November 25, 2010 may be read as "status quo",  as 
the  word "ante" is a mistake. Further, vide its order dated  December  22, 
2010, the Hon`ble Court while admitting the Writ Petition directed MoEF and 
Central and/or State level Environment Impact Assessment Authority to visit 
LCL`s  project at Lavasa and inspect it thoroughly for at least three  days 
to undertake the survey / inspection and pass an order by January 10, 2011. 
In  the same order dated December 22, 2010, the Hon`ble High Court  clubbed 
together  4  public interest litigations filed against LCL  (`other  PILs`) 
inter  alia  in  respect of lease of land  by  Maharashtra  Krishna  Valley 
Development   Corporation  to  LCL,  alleged  violations  by  LCL  of   the 
Maharashtra  Agricultural  Lands (Ceiling on Holdings) Act,  1961  and  the 
Environment (Protection) Act, 1986.

The  members  of  MoEF  committee along with  officials  of  Government  of 
Maharashtra visited Lavasa site on 5th, 6th and 7th of January, 2011.

Vide  its  order  dated  January 17, 2011, MoEF observed  that  LCL  is  in 
violation  of  EIA Notifications and the construction  activity  undertaken 
thereon  is  unauthorized, in violation of the above notifications  and  is 
environmentally damaging. However, taking into account the submissions made 
by  LCL,  employment generated, investments already made  and  third  party 
rights  already  accrued, MoEF stated that it is prepared to  consider  the 
project on merits with terms and conditions.

On January 24, 2011, LCL filed another Writ Petition being No. 811 of  2011 
in Bombay High Court challenging the aforesaid impugned order dated January 
17, 2011 passed by MoEF

On  January 27, 2011, Writ Petition no. 811 of 2011 and Writ  Petition  no. 
9448  of  2010  along with other PILs were listed in  Hon`ble  High  Court. 
However, the Hon`ble High Court, upon LCL`s plea was pleased to adjourn the 
matters  for  45  days  in view of the ongoing  discussions  with  MoEF  on 
amicable settlement and posted all LCL connected matters on March 10, 2011.

LCL on February 7, 2011 submitted a "without prejudice" application to MoEF 
for  Environment  Clearance (EC) and submitted various documents  to  MoEF, 
from time to time, for its consideration.

LCL attended & presented at the 97th & 98th meeting of the Expert Appraisal 
Committee  (`EAC`) on CRZ, Infrastructure & Miscellaneous Projects and  New 
Construction  and  Industrial  Estates Projects scheduled on  14th  &  15th 
February,  2011  &  3th & 4th March, 2011 respectively  at  New  Delhi  and 
submitted various supporting documents and also made oral representation.

The minutes of the 98th meeting of EAC held on 3rd & 4th March, 2011 at New 
Delhi  inter  alia  state  that, the EAC recommends that  in  view  of  the 
investments  made by the third parties, infrastructure already  created  in 
the  Dasve  village and taking note of the reported  hardships  highlighted 
repeatedly by LCL of the construction workers, pending construction work of 
257  residential  buildings, which are above plinth level, may  be  allowed 
subject  to  certain  conditions  such as (i)  no  hill  cutting,  digging, 
excavation, etc, (ii) the above constructions shall only be limited to  the 
area for which permission was granted by the Collector, Pune, (iii) a  high 
level  Verification  and Monitoring Committee shall  be  constituted,  (iv) 
commitment from LCL to earmark necessary / adequate funds as per report  to 
be  submitted  shortly  regarding the quantum of  penalty/  recompense  and 
creation  of  Environmental Restoration Fund and (v)  other  conditions  as 
stipulated by MoEF / other State agencies of State Government shall also be 
complied with.

In  view  of the above stipulations, the Committee recommended to  MoEF  to 
permit  LCL  to complete 257 units subject to the acceptance  of  the  five 
conditions  listed  above and also subject to submission of  information  / 
documents as per the above observations.

Further EAC also stated that consideration of the proposal would depend  on 
submission of the requisite information as detailed above.

On  March 30, 2011, LCL filed an application to withdraw the Writ  Petition 
no. 811 of 2011 and Writ Petition no. 9448 of 2010 with a liberty to file a 
fresh one as and when need arises. On hearing all the parties including PIL 
litigants,  the Hon`ble High Court suggested that in order to take care  of 
the  apprehensions  of the PIL litigants, LCL`s counsel  and  MoEF  counsel 
should make a statement that status quo order dated January 17, 2011 passed 
by  MoEF  should continue to operate till show cause notice is  decided  by 
MoEF.  LCL was of the view that its writ petitions should not be  withdrawn 
with  such  an  adverse order and hence decided not to  withdraw  its  writ 
petitions and matter was then adjourned to June 15, 2011.

On April 6, 2011 LCL attended the 99th meeting of EAC and made presentation 
before  members  of  EAC and replied to the queries raised by  the  EAC  in 
relation  to  the vacation of status quo on the construction work  in  area 
admeasuring  681.27  hectares,  pending  consideration  of  its  1st  phase 
Environment Clearance (EC) of 2000 Hectares. As per the Minutes of the 99th 
Meeting  of  EAC,  EAC  decided that proposal of  the  Company  for  681.27 
hectares  be  deferred and be considered along with the whole  proposal  of 
2000 hectares.

LCL  vide its letter dated April 30, 2011 submitted para wise reply to  the 
points  raised  by the EAC in its 99th Meeting & requested to grant  EC  to 
681.27 Hectares.

On April 12, 2011, LCL as per the directions of the EAC, submitted  revised 
Environment  Impact  Assessment report and baseline data /  maps  etc.  The 
100th meeting of the EAC took place on May 12, 2011. LCL made  presentation 
in  relation to the queries raised in the previous meeting with respect  to 
the application for EC for 1st Phase (2000 hectares). On May 21, 2011,  LCL 
submitted  para wise reply to the points raised in the EAC`s 100th  meeting 
dated May 12, 2011. On May 31, 2011 the senior officials of LCL along  with 
consultants  attended  the 101st meeting of EAC and  made  presentation  in 
relation to the queries raised in the previous meeting. As per the  Minutes 
of  the  101st  meeting the EAC recommended the  proposal  for  Environment 
Clearance  for the 1st Phase (2000 hectares) with the conditions  mentioned 
therein. On June 10, 2011 MoEF directed to the Government of Maharashtra to 
initiate  necessary legal action under Environment (Protection),  Act  1986 
against LCL.

On June 15, 2011 LCL`s Writ Petition No. 811 of 2011 and Writ Petition  No. 
9448 of 2010, were listed on board in the Bombay High Court. The MoEF filed 
an  Affidavit  in the Company`s Writ Petitions stating  that  ministry  has 
accepted  the recommendations of EAC subject to preconditions. The  learned 
Additional  Solicitor General appearing for MoEF stated that the MoEF  will 
be passing an order within a reasonable time. The matter was then adjourned 
to  July 12, 2011. On June 27, 2011 MoEF, Government of India  addressed  a 
letter  to LCL thereby enclosing the Minutes of the 101st Meeting  held  on 
May  31,  2011  and  also informed  the  five  pre-conditions.  It  further 
requested  LCL to submit all the documents as per the  pre-conditions.  The 
five  pre-conditions,  reproduced verbatim, are:-i)   The  constructions  / 
development   carried  out  till  now  are  in  violation  of   Environment 
(Protection),  Act 1986. The violation has to be dealt as per OM No.  No.J-
11013/41/2006-IA. II (I) dated November 16, 2010. As per 4(ii) of the above 
OM, LCL shall submit a written commitment within 90 days, in the form of  a 
formal resolution from Board of Directors of the Company for  consideration 
of  its  environment  related policy / plan of action to  the  Ministry  to 
ensure  that violation of the Environment (Protection), Act etc. shall  not 
be repeated.

ii) The scale and intensity of development of the hill town shall be as per 
Hill  Station  Regulations  and shall be revised  based  on  developable  / 
buildable area. A clear demarcation of "no development / construction  zone 
/  area" shall be identified comprising of (a) all water bodies (b)  forest 
lands / forest like lands and (c) areas steeper than 1:3. The developable / 
buildable  areas shall be verified through State  Government/Director  Town 
Planning  and  the  calculation  of  FSI  shall  be  made  accordingly.  No 
development shall be taken up in areas steeper than or equal to 1:3.

iii)  The FSI calculation shall be worked out separately based on the  land 
uses and shall not be averaged for the calculation of FSI.

iv)  At  least  5 % of the total cost of the  project  shall  be  earmarked 
towards  the  Corporate Social Responsibility (CSR) and  item-wise  details 
alongwith  time  bound action plan shall be prepared and submitted  to  the 
Ministry`s Regional Office at Bhopal. Implementation of such program  shall 
be ensured accordingly in a time bound manner.

v)  LCL  shall submit an undertaking / commitment to  earmark  necessary  / 
adequate funds as per report to be submitted shortly regarding the  quantum 
of penalty / re-compense and creation of Environment Restoration Fund.

On  July  12, 2011 LCL sent an e-mail and a letter to the  Director,  MoEF, 
requesting for hearing on the pre-conditions mentioned in the letter  dated 
June 27, 2011 as the same were unreasonable.

On July 27, 2011 LCL vide its letter submitted to MoEF its case in  respect 
of  the  pre-conditions  and also requested that the case  of  LCL  may  be 
processed further for appropriate decision without waiting for the date  of 
hearing which was scheduled for August 5, 2011.

Further,  on August 5, 2011 the officials of LCL appeared before the  panel 
and  made written submission along with the Board Resolution in respect  of 
the  pre-conditions as stated in MoEF`s letter dated June 27,  2011.  Thus, 
LCL complied with the pre-conditions as stated by MoEF.

Considering  the  delay  by  MoEF in issuing EC,  LCL  filed  another  Writ 
Petition  on  August  30, 2011 in the Hon`ble  Bombay  High  Court  seeking 
directions  interalia that (a) it be declared that LCL has been  granted  / 
deemed  to  have been granted environmental clearance for Phase  I  of  the 
project  or in the alternative (b) the Hon`ble Court be pleased to issue  a 
writ  of  mandamus  or  a  writ in the nature  of  mandamus  or  any  other 
appropriate  writ,  order  or  direction  commanding  the  MoEF,  to  grant 
environmental clearance to Phase I.

On  September  5,  2011 LCL`s Writ Petitions along with  other  PIL`s  were 
listed  on board. The counsel for MoEF submitted that they will pass  final 
order by September 23, 2011.

On  September  23,  2011 all related matters were listed  on  board.  After 
hearing the parties, Hon`ble High Court granted three weeks time as  prayed 
for  by the Ld Additional Solicitor General appearing for MoEF for  passing 
the  final order. The Hon`ble High Court made clear that this  three  weeks 
time  is  granted  by way of a last chance for  passing  final  order.  The 
matters were adjourned to October 18, 2011.

On  October 13, 2011, MoEF passed an order thereby communicating  that  "As 
the pre-conditions on the credible action on violation of EIA  Notification 
2006 has not been complied with, the Ministry is unable to issue the EC  to 
the  1st  phase of Hill City project (2000 hectares) of Lavasa.  The  final 
decision  on  the EC cannot be taken till all the  pre-conditions  are  met 
including  credible  action  by the State  Government  of  Maharashtra  and 
subject  to final orders of the Hon`ble High Court of Bombay as the  matter 
is sub-judice".

On October 20, 2011 all LCL matters were listed on board of Hon`ble  Bombay 
High Court. LCL`s Counsel also pointed out that time and again the MoEF has 
sought for adjournments but failed to pass the final order and the inaction 
on  the part of MoEF in not passing final order would virtually  amount  to 
misleading the Court. The Ld. Special Counsel for the State made  statement 
that the State Government will initiate necessary action in accordance with 
the  law,  against  LCL within two weeks. Thereafter MoEF  Counsel  made  a 
statement  that MoEF will pass final order within one week  thereafter.  In 
view of the statements made by the respective counsels for State Government 
and  MoEF,  the Hon`ble court gave three weeks time to MoEF to  pass  final 
order  as prayed for and observed that this three weeks time shall  not  be 
extended  in any circumstances. The matters were adjourned to November  16, 
2011.

On  November  4, 2011, Maharashtra Pollution Control Board (MPCB)  filed  a 
criminal  complaint  against  LCL & 14 Others  before  the  Chief  Judicial 
Magistrate, Pune under Section 15 and 16 of the Environment Protection Act, 
1986  (EP  Act)  for  alleged  violations of  the  EP  Act  read  with  EIA 
Notification 2006.

On November 9, 2011, MoEF passed an order and pursuant to the same accorded 
Environment  Clearance  to  the 1st phase of the  LCL  project  subject  to 
certain conditions as mentioned therein.

On  November 16, 2011 all LCL matters were listed on board. MoEF filed  its 
affidavit  in  reply to LCL Writ Petition no. 7276 of  2011.  Matters  were 
adjourned to December 12, 2011.

On November 17, 2011 LCL submitted certain documents to The Deputy Director 
(I.A),  in  compliance of Condition No. ii Part A  -  Specific  Conditions, 
Construction Phase.

On November 24, 2011 the Chief Judicial Magistrate, Pune passed an order of 
issuance  of  process  in  the Criminal matter  and  the  matter  was  then 
adjourned to January 30, 2012.

On December 6, 2011 LCL vide its without prejudice letter addressed to  The 
Advisor, I A Division of MoEF, requested for exclusion of the K T Ravindran 
committee  report  from  the  EC order dated  November  9,  2011  and  also 
requested for a hearing. On December 7, 2011 LCL vide its without prejudice 
letter addressed to The Advisor, I A Division of MoEF, informed that  there 
are  certain discrepancies and contradictions in the EC dated  November  9, 
2011  and  requested for reconsidering the pre-condition no (iv)  and  also 
requested to withdraw the same. LCL also addressed a letter to The Advisor, 
I  A  Division  of  MoEF, and requested to furnish  papers  i.e.  Terms  of 
Reference (TOR) of Prof K T Ravindran Committee, interim report dated March 
7, 2011 presented by expert committee to MoEF, notings made by each of  the 
members of the K T Ravindran committee, etc.

On December 9, 2011 LCL filed Appeal being no. 36 of 2011, u/s 16(h) of the 
National Green Tribunal Act against The Union of India, MoEF & Anr,  before 
the National Green Tribunal (NGT) at Delhi, for challenging part of the  EC 
order  dated  November  9,  2011 more particularly  about  the  Prof.  K  T 
Ravindran Committee Report and the conditions imposed by it.

On December 12, 2011 all LCL matters alongwith other connected matters were 
listed  on  board  before  Hon`ble Bombay  High  Court.  The  matters  were 
adjourned to January 31, 2012.

On  January  10, 2012 LCLs Appeal No. 36 of 2011 filed before  NGT  was  on 
board and the Tribunal was pleased to pass order "Notice before  Admission" 
and the matter was adjourned to February 17, 2012.

On January 30, 2012 Criminal Complaint filed by MPCB was on board of  Chief 
Judicial Magistrate, Pune and the same was adjourned to March 17, 2012.

On January 31, 2012 all LCL matters along with other connected matters were 
listed on board before Hon`ble Bombay High Court, Division Bench of Justice 
Bobde & Justice Dhanuka. The Bench recsued to hear the LCL matters.

On February 6, 2012 one of the villager Shri Dyneshwar Shegde filed  Appeal 
(being  No. 9 of 2012) before Hon`ble National Green  Tribunal  challenging 
the EC order dated November 9, 2011 passed by MoEF in favour of LCL.

On February 17, 2012 NGT Appeal filed by LCL was listed on board of Hon`ble 
Tribunal at Pune and the same was adjourned to April 16, 2012.

On  February  21, 2012 all LCL matters along with other  connected  matters 
(except  PIL (L) 90 of 2010 & WP 2737 of 2011) were listed on board  before 
Hon`ble Bombay High Court Division Bench of Justice Khanvilkar & Justice  N 
Jamdar.  The  Bench  recsued  to hear LCL matters  as  Justice  Jamdar  had 
appeared for MoEF.

On  February  22, 2012 Shri Dyneshwar Shegde`s Appeal was on  board  before 
Hon`ble NGT, Delhi. LCL intervened in the matter & opposed the  application 
for  condonation of delay filed by the Appellant. The matter was  adjourned 
to March 20, 2012.

On  March  17, 2012 Criminal Complaint filed by MPCB was  on  board  before 
Chief  Judicial  Magistrate, Pune and the same was adjourned to  April  20, 
2012.

On  March  20,  2012 Shri Dyneshwar Shegde`s Appeal  was  on  board  before 
Hon`ble  NGT,  Delhi.  LCL  filed  its  affidavit  in  reply  opposing  the 
application for condonation of delay filed by the Appellant. The matter was 
adjourned to April 12, 2012.

On  April  12,  2012 Shri Dyneshwar Shegde`s Appeal  was  on  board  before 
Hon`ble  NGT  New  Delhi.  Submissions were made  by  the  parties  on  the 
application for condonation of delay in which the parties apprised the  NGT 
on  the facts of the appeal. Advocate for Dyneshwar Shedge prayed for  time 
to  file rejoinder. The Hon`ble NGT directed him to file  rejoinder  before 
April 18, 2012. The matter was adjourned to April 24, 2012.

On  April 16, 2012 NGT Appeal filed by LCL was listed on board  of  Hon`ble 
NGT  at  New Delhi. The Hon`ble NGT directed MoEF and MPCB  to  file  their 
affidavits before July 2, 2012. The matter was adjourned to July 19, 2012.

On  April  20, 2012 Criminal Complaint filed by MPCB was  on  board  before 
Chief Judicial Magistrate, Pune and the same was adjourned to May 14, 2012.

On  April  24, 2012 Dyneshwar Shegde`s Appeal was on board  before  Hon`ble 
NGT,  New Delhi. The Advocate for Appellant filed rejoinder.  Arguments  by 
all  the parties got concluded. The Hon`ble NGT has reserved the Order.  No 
further date is fixed.

ii) HCC Real Estate Ltd.

HCC Real Estate Ltd (HREL), a wholly owned subsidiary of your Company,  has 
inherent skills and resources to develop and deliver high-value real-estate 
projects  that  helps in building sustained communities across  India.  The 
focus  is to develop `state-of-the-art` projects which would provide  world 
class  quality,  engineering  and  technology and  create  a  unique  value 
proposition for the customers.

Project Management Services

With  successful and timely completion of 247Park, the  Project  Management 
department  of  the  Company  was  entrusted  with  the  responsibility  of 
providing Project Management Consultancy (PMC) for various projects for our 
associate  companies such as Charosa Wineries Ltd.,  Panchkutir  Developers 
Ltd.  The scope of the work included project management, health-safety  and 
environment management.

After completing these projects, the project management team is hopeful  of 
getting  some  projects  from  external  clients.  In  the  present  trying 
circumstances,  income from the project management consultancy business  is 
expected  to add to the revenue of the Company by utilizing  the  technical 
skills available within the Company.

Projects under execution

1. 247 Park Phase II

The Company has initiated the regulatory process for obtaining the approval 
for development of commercial office building with approx. 400,000 sq ft of 
saleable  area  and  approx. 800,000 sq ft  total  construction  area.  The 
project  is  based on the "Public-Parking Policy"  finalised  by  Municipal 
Corporation  of Greater Mumbai (MCGM) for which the Company  has  submitted 
the  application. The Company has received preliminary approvals  from  Jt. 
Commissioner-Traffic  for 520 car parks on the basis of  extensive  traffic 
surveys  conducted  by traffic consultants.  Subsequently  the  architects, 
structural engineers and traffic consultants have prepared the reports  for 
submission to the Parking committee constituted by MCGM which has  approved 
location  and  detailed  building drawings of  the  scheme  afte  extensive 
reviews.  The  Company has also commenced work on acquiring  various  other 
NOC`s including from Fire Department of MCGM.

During  the year, the project team has conducted prequalification  exercise 
for  the  civil  and other contractors for  the  construction  The  Company 
envisages  completion  of  the construction of the  project  by  2014.  The 
marketing  and  sales department of the Company has submitted  Request  for 
Proposals (RFP) for built-to-suit (BTS) commercial office space requirement 
and the Company is hopeful of receiving good response riding on the success 
of 247Park Phase I.

2. Urban Renewal (Slum Re-development Project), Powai

MOU-cum-Development  Agreement and Power of Attorney were executed by  land 
owner in favour of the SPV, Panchkutir Developers Ltd , a subsidiary of HCC 
for  12  acres  of land. Due to non performance by the land  owner  of  the 
various  obligations  under the MOU-cum-Development  Agreement  inspite  of 
repeated  reminders,  we have been advised by our solicitor to  invoke  the 
Arbitration  clause  forming  part of  the  MOU-cum-Development  Agreement. 
Accordingly,  Arbitration  proceedings  have been  initiated  and  we  have 
obtained interim orders.

3. Urban Renewal (Slum Re-development Project), Vikhroli (E)

Out  of  the  total  land holding of around  32  acres  by  the  Panchkutir 
Developers Ltd. in Vikhroli (E), the survey of tenements on Phase-I of 14.5 
acres  of  land  to ascertain the development potential of  the  free  sale 
component  is completed. Out of the 1960 slum residents, consent  of  about 
1400 residents representing more than 70% has already been obtained and the 
process  for  forming  the  society is in progress.  Out  of  the  proposal 
submitted  to Slum Redevelopment Authority (SRA) for Phase-I of about  2000 
slums, Annexure II has been displayed for 750 tenants of 4 Societies &  for 
the  balance the work is in progress. Slum declaration of Phase-I  land  is 
challenged  which  has  been  set  aside  by  the  Special  Slum  Tribunal. 
Subsequently  the litigant filed Writ Petition challenging the  above  said 
Order of the Slum Tribunal in High court. Hearings from both the sides  are 
completed and the judgment is awaited.

4. Integrated Township Development, Thane

HRL (Thane) Real Estate Ltd. a subsidiary of HREL initiated the acquisition 
of land at Ghodbunder Road, Thane for Integrated Township Development. Till 
date the Development Agreement and Power of Attorney for 32 acres have been 
executed  in favour of the Company. The Company continued its  activity  of 
securing its position for land title and other documentation.

5. Integrated Township Development ,Pune near Hinjewadi IT Park (Phase 1)

Maan Township Developers Ltd, a subsidiary of HREL has acquired approx.  28 
acres of land and the Development Agreement and Power of Attorney have been 
executed  in  favour  of Company. The Company  continued  its  activity  of 
securing its position for land title and other documentation.

6. Integrated Township Development Land, Wadiwarhe, Nashik

Nashik  Township Developers Ltd a subsidiary of HREL has acquired 62  acres 
of  land  for which Development Agreement and Power of Attorney  have  been 
executed in favour of Company. The Company is exploring sale option as well 
as various development options with education service providers in view  of 
improved connectivity to the region.

7. Water Front City at Dholera ,Gujarat

HCC signed MOU with Government of Gujarat for setting up of proposed  Water 
Front  City  covering 4000 acres and Renewable Energy  Park  covering  1500 
acres  at Dholera SIR with total proposed investment of  Rs. 52,000  crore. 
The  Company  finalised the "Vision Statement" for  development  of  "Water 
Front

City"  after discussion and meetings with Gujarat Government Officials  and 
Ministers.  The Company is exploring joint development  opportunities  with 
Samsung C & T Corporation and other reputed developers. Concept Development 
Report  on  proposed  City has been  submitted  to  Gujarat  Infrastructure 
Development  Board (GIDB). Proposal of allotment of 1900 acres of  land  in 
Bavliyari  Village  has  been  received  from  Govt.  of  Gujarat.   Letter 
requesting  land  in  Zone 1 (TP1) & Zone 2 (TP2)  closer  to  Ahmedabad  & 
payment  terms  has  been  sent  to  Dholera  Special  Investment  Regional 
Development  Authority  (DSIRDA).  The  discussion on  the  subject  is  in 
progress.

8.  Charosa Wineries Limited, Dindori, Nashik

Till date purchase of total 211 acres of land has been completed.  Purchase 
of  another  27 acres of land is in progress as on date.  Total  land  area 
under  cultivation is 81 acres. During the year, the Company signed  a  PMC 
agreement  with the Project Management Team of HREL for  providing  project 
management,  health-safety  and  environment  management.  Construction  of 
Winery Building is at an advanced stage. The Company has received  approval 
to  procure  land under Section 63-1A of Bombay  Tenancy  and  Agricultural 
Lands  Act  (BTAL)  for Wine Tourism Project. The  Company  has  also  been 
accredited  under "Mahabhraman" scheme of Maharashtra  Tourism  Development 
Corporation   (MTDC)  to  operate  tour  packages  within  the   state   of 
Maharashtra.  Further the Company has obtained registration from MTDC as  a 
service provider for tourism.

Internationally  renowned  Master Planners and Architects,  HOK  have  done 
master  planning for setting up wine tourism project consisting of  tourist 
resorts, cellar-doors, wine bars, restaurant, theme park, adventure sports, 
amphitheater, Wine spa etc. Harvesting and crushing of nearly 200 MT grapes 
has  been completed during the year. During the year Company  fully  repaid 
the loan taken from the bankers.

(iii) HCC Infrastructure

HCC Infrastructure Company Ltd, a wholly owned subsidiary of your  Company, 
has  in its  Rs. 5,500 crore portfolio, six National Highways Authority  of 
India (NHAI) road concessions.

The Company, through its subsidiaries HCC Concessions and HCC Power, has  a 
development  focus  primarily in the roads, water and power  sectors.  Your 
Company   follows   a  disciplined  investment  strategy   that   maximizes 
shareholder value by generating stable and rapidly growing streams of  cash 
flow over concession periods ranging from 15 to 30 years. Besides obtaining 
a construction edge provided by HCC`s E&C division, HCC Infrastructure  has 
developed  a  strong management team whose expertise extends  from  concept 
innovation and evaluation of risk & return, to construction management  and 
operations. Along with a focus on quality and timely execution, the Company 
is  committed  to  provide reliable, safe and world  class  operations  and 
maintenance services to the country`s end users.

Fund Raising Initiative:

Your  directors  are  pleased to inform you that  in  September  2011,  HCC 
Infrastructure  Co.  Ltd, wholly owned subsidiary Company raised   Rs.  240 
crore by diluting 14.5% equity stake in HCC Concessions to the Xander Group 
at  an  equity  valuation of  Rs. 1,650 crore. This  equity  placement  was 
completed  during  challenging  market conditions and  showcases  both  the 
quality  of the HCC Infrastructure`s portfolio and the conviction in  their 
management team. The Xander Group Inc. is a global investment firm  focused 
on  the infrastructure, hospitality, retail and real estate sectors.  Since 
2005,  the firm has committed over US$1.8 billion of equity capital to  the 
Indian  market  across  five dedicated India funds.  Your  Company  remains 
committed  to capital raising at attractive valuations to meet  its  equity 
requirements for future growth.

Current Road Portfolio:

Your  directors  are pleased to inform you that during the  course  of  the 
year, the Company successfully achieved the provisional completion of Dhule 
Palesner Highway project and started toll collection on February 11,  2012, 
four  months  ahead of schedule. This is the third such  consecutive  early 
completion,  showcasing our project management and construction  expertise. 
Toll collection is significantly ahead of estimates and is expected to grow 
strongly.

The three highway projects in West Bengal (NH34) are under construction and 
traffic  growth  on  the road over the past  two  years  has  significantly 
exceeded expectations.

During  the year, HCC Concessions submitted 9 NHAI bids and 28 Request  for 
Qualification

(RFQs). HCC Concessions partnered with VINCI Concessions for certain  large 
bids to diversify risk and increase competitiveness. While your Company was 
unsuccessful  in  procuring  a new project this  year,  it  maintained  its 
investment  discipline  while  observing  that  several  competitors   were 
aggressively obtaining projects at detrimental or unsustainable values. The 
Company will continue to bid for NHAI projects in the next financial  year, 
where approx. 8,000 km of roads is expected to be awarded. Your Company  is 
also evaluating state road opportunities.

Status of Operational Assets:

Dhule Palesner Highway Project (NH3)

The project started user fee collection in February 2012, four months ahead 
of  schedule.  In FY09, NHAI awarded the development of four  lane  highway 
from  Km  168.500  to  Km  265.000 on  the  Maharashtra/MP  border  to  the 
consortium led by HCC Concessions on BOT (toll) basis.

The  project  road  (89  km) starts at Dhule in  Maharashtra  and  ends  at 
Palesner  on  the border of Maharashtra and MP on National Highway  3.  The 
project  is being operated by an in-house operations and maintenance  team. 
The  concession period is 18 years, including a construction period  of  30 
months.  The  highway  is  being  developed  in  partnership  with  Sadbhav 
Engineering  Ltd and John Laing Investments Ltd (UK) with an investment  of  
Rs. 1,420 crore.

Delhi Faridabad Elevated Expressway (NH2) (dfskywayT)

The  dfskywayT started user fee collection in November 2010.  This  project 
was also completed ahead of schedule. The project road is a 4.4 km elevated 
highway connecting Delhi and Faridabad, Haryana and serves inter-state  and 
local  traffic. With immediate connectivity for Faridabad to the  heart  of 
Delhi due to dfskywayT, one expects much higher growth for Faridabad, which 
has  recently  been cited as the 8th fastest developing city  by  The  City 
Mayors Foundation, UK.

The project has remaining concession period of approximately 17 years.  HCC 
was  awarded a 20-year concession in 2008 to design, construct and  operate 
this asset by the NHAI.

Nirmal (NBL) Annuity (NH7)

The  SPV  has received timely annuity payments over the last year  and  the 
operations  and maintenance are being managed efficiently by our  in  house 
team.

The  project stretch extends from the Maharashtra-Andhra Pradesh Border  to 
Armur in Andhra Pradesh, which forms a part of the Nagpur-Hyderabad section 
of  NH7.  This  is the sole Annuity project in our portfolio.  This  33  km 
project  was  completed about 100 days ahead of scheduled  completion.  The 
remaining concession period for the project is 15.5 years. The project  was 
developed by HCC with an investment of  Rs. 315 crore.

Status of Assets under Development:

West Bengal (NH34) Highway Project

This  highway  project  includes  three contiguous  sections  (256  km)  on 
National Highway 34, starting from Baharampore and ending at Dalkhola.  The 
construction  of  this  highway project is underway and  your  Company  has 
achieved  considerable progress over the last year. Though NHAI  has  found 
the  land  acquisition process along the project  stretch  challenging  and 
final  completion is likely to be delayed by a few months due to  this,  we 
expect  that  the  project  would start  tolling  by  originally  scheduled 
completion date (on 75% completion). The project is being solely  developed 
by HCC with an investment of  Rs. 3,232 crore.

Baharampore Farakka Highway

This  section,  awarded  in  FY10,  is a  103  km  stretch  originating  at 
Baharampore and terminating at Farakka. The concession period is 25  years, 
including  a  construction  period  of 30  months.  The  project  is  being 
implemented  with  an  investment  of  Rs.  1,169  crore.  Farakka  Raiganj 
Highway.

This is a 103 km stretch originating at Farakka and terminating at Raiganj. 
The  concession period is 30 years, including a construction period  of  30 
months.  The project is being implemented with an investment of  Rs.  1,378 
crore.

Raiganj Dalkhola Highway

This is a 50 km stretch starting at Raiganj and terminating at the town  of 
Dalkhola.  The  concession period is 30 years and includes  a  construction 
period of 30 months. The project is being implemented with an investment of  
Rs. 684 crore.

(iv) Steiner AG, Switzerland

Your Company holds through its wholly owned HCC Mauritius Enterprises  Ltd. 
a controlling equity stake of 66% in Steiner AG (formerly Karl Steiner AG). 
Steiner  AG  is  a  leading general  contracting  Company  in  Switzerland, 
specialized in turnkey development of new buildings and refurbishments, and 
offers services in all facets of real estate development and construction.

Steiner AG had a consolidated revenue of Rs.3996.2 crore and a consolidated 
profit  before tax of  Rs. 20.8 crore in the period from April 1,  2011  to 
March 31, 2012.

After  three years of construction, Steiner AG completed the  Prime  Tower, 
Switzerland`s  highest building (126 meters high), in collaboration with  a 
partner.  With 36 floors, usable surface of 40,000 sqm and space for  2,000 
work places, the Prime Tower is a landmark for the whole region.

In  the business year 2011-12 Steiner AG signed many  important  contracts, 
which  include  the project Neue Schanzenpost/PostParc in  Berne,  a  total 
services  contract of around CHF 160 million with Swiss Post as  client,  a 
general  contract for the project Mehr als Wohnen in Zurich, consisting  of 
13 apartment buildings and a range of office spaces and business  premises, 
for a total volume of around CHF 145 million and a total services  contract 
for project Lindbergh in Zurich, a large-scale building for mixed use  with 
Credit Suisse as investor with a total volume of around CHF 100 million.

At year end, the order backlog of Steiner AG was CHF 1512 million  compared 
to  CHF  1018  million as of March 31, 2011. Steiner AG  has  also  secured 
projects worth CHF 135 million which are yet to be signed.

By  the end of July 2011, Steiner AG relocated into its  new  headquarters, 
which is located in Andreaspark Business Centre in Zurich and was developed 
and realized by Steiner AG. Steiner AG also changed its corporate name from 
"Karl  Steiner  AG  (Karl Steiner SA) (Karl Steiner Ltd)"  to  "Steiner  AG 
(Steiner  SA)  (Steiner  Ltd)".  The new  name  became  official  with  the 
relocation of Steiner AG to its new headquarters.

To  help achieve your Company`s goal of extending its footprint in  India`s 
growing   residential  and  commercial  construction  market,  Steiner   AG 
incorporated a wholly owned subsidiary in Mumbai under the name of  Steiner 
India  Limited. The new entity will undertake construction of  real  estate 
projects in India.

The  board of directors of Steiner AG comprises five members. Your  Company 
is  represented  by three nominees: Mr. Ajit Gulabchand, who also  acts  as 
Chairman, Mr. K.G. Tendulkar and Mr. Anil Singhvi.

v) Highbar Technologies Ltd

Highbar Technologies Ltd, a wholly owned subsidiary of your Company, is  an 
Information  Technology Company formed by your Company, with the vision  of 
providing end-to-end IT solutions to Infrastructure industry.

Highbar  Technologies`  core  team  comprises  of  IT  and   Infrastructure 
professionals  who have amalgamated the legacy of domain knowledge  in  the 
infrastructure business with Information technology. Highbar focuses on  IT 
implementation initiatives from business transformation perspective  rather 
than technology implementation perspective.

This  year, Gartner- one of the world`s most renowned IT  research  agency, 
has published case study on managing successful IT spin-off with Highbar as 
an example. After a long time they could locate a successful spin-off worth 
writing case study on it. Industry experts have recognised it as Asia`s 1st 
IT  Company  for  Infrastructure  industry` and have  shown  faith  in  its 
capabilities as against big established IT players.

In  the last financial year, Highbar Technologies was able to serve 10  new 
customers,  taking  the total tally of its customers to 50.  Long  list  of 
reference customers and high quantum of repeat business indicates  maturity 
of Highbar`s delivery capabilities.

In order to serve Infrastructure industry in Middle East more  effectively, 
Highbar  Technologies  Ltd, has incorporated a subsidiary in  Dubai,  named 
`Highbar Technologies FZ-LLC` which is now fully operational and has bagged 
customers in Middle East.

IT adoption in Infrastructure industry has gathered pace. Highbar sees  the 
business  going places and will expand beyond India and Middle  East.  This 
year  the Company has developed a very strong strategic alliance  with  SAP 
who  considers Highbar as a preferred partner for infrastructure  industry. 
The  Company  launched  new  solutions -  Highbar  RapidStart  and  Highbar 
CloudConnect-which  provide preconfigured SAP ERP solutions on-premise  and 
on-cloud  respectively.  These  solutions  are  based  on  the  templatised 
approach   and   are  Intellectual  Property  (IP)   assets   for   Highbar 
Technologies. Highbar Technologies has strategically entered into a  tie-up 
with  SAP to launch Highbar CloudConnect, which offers 1st of its kind  SAP 
ERP  solution  for  infrastructure,  real estate  and  ready  mix  concrete 
industry  on pay-per-user-per-month basis. This has provided SMEs  a  level 
playing  field by getting access to world-class IT solutions  and  industry 
best  practices in an investment friendly model. The cloud based  offerings 
have helped Highbar Technologies to penetrate the industry further to  next 
level by reaching to the masses.

Highbar   also  successfully  implemented  first  comprehensive   SAP   CRM 
implementation  for Indian construction industry which won SAP  ACE  Award. 
Highbar  continues  to  compete  consistently with  the  big  names  in  IT 
industry.  It  has  created niche for itself in the market  with  a  firmly 
established  grounds. It has started contributing to the industry  to  grow 
`IT for infrastructure market`.

Highbar  Technologies  has  established  a  proper  scalable   organization 
structure with all the functions in place to facilitate and sustain  future 
growth.

Highbar  Technologies is on the course towards accomplishing its vision  of 
being   `the  most  preferred  end  to  end  IT  solution   provider`   for 
infrastructure industry.

5. Subsidiary Companies

At the beginning of the year, the Company had 67 Subsidiary Companies.

During the year under review, the following changes have taken place.

a)  HCC  Infrastructure Co. Ltd (the wholly owned subsidiary  Company)  has 
promoted  the  following  wholly  owned subsidiary  Company,  making  it  a 
subsidiary of your Company from the date of its incorporation.

Name of the Company                     Date of Incorporation

Dhule Palesner Operations &             18.05.2011 
Maintenance Limited

HCC Power Limited                       03.06.2011

b)  Steiner  AG (a subsidiary Company) has promoted  the  following  wholly 
owned  subsidiary Company, making it a subsidiary of your Company from  the 
date of its incorporation.

Name of the Company                     Date of Incorporation

Steiner India Limited                   17.08.2011

(c)  Lavasa  Corporation Limited (a subsidiary Company)  has  promoted  the 
following  companies making them subsidiaries of your Company from the  day 
of their incorporation.

Name of the Company                     Date of Incorporation

Warasgaon Assets                        24.06.2011 
Maintenance Limited

Hill View Parking Services              24.06.2011 
Limited

In  terms  of the General Circular No. 2/2011 dated February 8,  2011  read 
together  with General Circular No. 3/2011 dated February 21, 2011,  issued 
by  the Government of India - Ministry of Corporate Affairs  under  Section 
212(8) of the Companies Act, 1956, granting general exemption to  companies 
from attaching financial statements of subsidiaries, subject to fulfillment 
of  conditions stated in the circular, copies of the Balance Sheet,  Profit 
and  Loss Account, Report of the Board of Directors and Auditors Report  of 
the subsidiary companies for the year/period ended December 31,  2011/March 
31,  2012  are  not attached to the Balance Sheet of  the  Company  as  the 
Company has/shall fulfill the following conditions:

(i)  The Board of Directors of the Company has vide resolution dated  April 
27, 2012 consented for not attaching the balance sheet(s) of the  concerned 
subsidiary(ies);

(ii)  The  Company  has presented in its Annual  Report,  the  consolidated 
financial  statements of holding Company and all of its  subsidiaries  duly 
audited by its statutory auditors;

(iii)  The  Consolidated financial statement has been  prepared  in  strict 
compliance  with  applicable  Accounting Standards  and  where  applicable, 
Listing  Agreement  as prescribed by the Securities and Exchange  Board  of 
India;

(iv)  The  Company  has disclosed in the  consolidated  balance  sheet  the 
following formation in aggregate for each subsidiary including subsidiaries 
of  subsidiaries:-  (a)  Capital (b)reserves (c)  total  assets  (d)  total 
liabilities  (e)  details of investment (except in case  of  investment  in 
subsidiaries)  (f)  turnover (g) profit before taxation (h)  provision  for 
taxation (i) profit after taxation (j) proposed dividend, as applicable;

(v)  The  annual  accounts and other related detailed  information  of  the 
following  subsidiaries  shall  be made available to  shareholders  of  the 
holding  Company and subsidiary companies seeking such information  at  any 
point of time :

1. Hincon Technoconsult Ltd

2. Western Securities Ltd

3. Pune-Paud Toll Road Company Ltd

4. Nirmal BOT Ltd

5. Panchkutir Developers Ltd

6. HCC Concessions Ltd (Formerly known as HCC Infrastructure Ltd)

7. HCC Infrastructure Company Ltd

8. HCC Aviation Ltd

9. Badarpur Faridabad Tollway Ltd

10. Baharampore - Farakka Highways Ltd

11. Farakka - Raiganj Highways Ltd

12. Raiganj - Dalkhola Highways Ltd

13. Dhule Palesner Operations & Maintenance Ltd

14. HCC Power Ltd

15. HCC Construction Ltd

16. Highbar Technologies Ltd

16. Highbar Technologies FZ LLC

17. HCC Mauritius Enterprises Ltd

18. Klemanor Investments Ltd

19. Steiner AG (Formerly known as Karl Steiner AG)

20. Steiner Promotions et Participations SA

21. VM + ST AG

22. Eurohotel SA

23. Steiner (Germany) GmbH

24. Steiner Leman SAS

25. SNC Valleiry Route De Bloux

26. Steiner India Ltd

27. HCC Singapore Enterprises Pte. Ltd

28. HCC Real Estate Ltd

29. HRL Township Developers Ltd

30. HRL (Thane) Real Estate Ltd

31. Nashik Township Developers Ltd

32. Maan Township Developers Ltd

33. Charosa Wineries Ltd

34. Powai Real Estate Developers Ltd

35. HCC Realty Ltd

36. Lavasa Corporation Ltd

37. Lavasa Hotel Ltd

38. Apollo Lavasa Health Corporation Ltd

39. Lakeshore Watersports Company Ltd

40. Dasve Convention Centre Ltd

41. Dasve Business Hotel Ltd

42. Dasve Hospitality Institutes Ltd

44. Lakeview Clubs Ltd

45. Dasve Retail Ltd

46. Full Spectrum Adventure Ltd

47. Spotless Laundry Services Ltd

48. Lavasa Bamboocrafts Ltd

49. Green Hill Residences Ltd

50. My City Technology Ltd

51. Reasonable Housing Ltd

52.  Future City Multiservices SEZ Ltd (Formerly known as  Minfur  Interior 
Technologies Ltd)

53. Rhapsody Commercial Space Ltd

54. Valley View Entertainment Ltd

55. Andromeda Hotels Ltd

56. Sirrah Palace Hotels Ltd

57. Warasgaon Tourism Ltd

58. Our Home Service Apartments Ltd

59. Warasgaon Power Supply Ltd

60. Sahyadri City Management Ltd

61. Hill City Service Apartments Ltd

62. Kart Racers Ltd

63. Warasgaon Infrastructure Providers Ltd

64. Nature Lovers Retail Ltd

65. Osprey Hospitality Ltd

66. Starlit Resort Ltd

67. Warasgaon Valley Hotels Ltd

68. Rosebay Hotels Ltd

69. Mugaon Luxury Hotels Ltd

70. Warasgaon Assets Maintenance Ltd

71. Hill View Parking Services Ltd

72. Whistling Thrush Facilities Services Ltd

(vi) Further, the annual accounts of the subsidiary companies shall also be 
kept for inspection by any shareholder at the head office/registered office 
of  the Company and of the subsidiary companies concerned and  the  Company 
shall furnish a hard copy of the details of accounts of subsidiaries to any 
shareholder on demand;

(vii)  The  holding  as  well as subsidiary  companies  in  question  shall 
regularly  file  such  data  to  the  various  regulatory  and   Government 
authorities as may be required by them;

(viii)  The Company has given Indian rupee equivalent of the figures  given 
in  foreign currency appearing in the accounts of the subsidiary  companies 
along with the exchange rate as on closing day of the financial year;

6. Share Capital

Increase  in Paid up Share Capital - Issue of Equity Shares on exercise  of 
Employee Stock Options

During  the  year  under  review, upon exercise of  Stock  Options  by  the 
eligible employees under the Employee Stock Option Scheme, the Company  has 
allotted  77,500 Equity Shares of  Rs. 1 each at an exercise price of   Rs. 
21.70 per Equity Share.

Consequent  to  the  allotment  of Equity Shares  upon  exercise  of  stock 
options,  the  Paid  up Share Capital of the  Company  has  increased  from 
60,65,32,920  Equity  Shares of  Rs. 1 each aggregating   Rs.  60,65,32,920 
(Rupees  Sixty  Crore  Sixty Five Lakhs Thirty Two  Thousand  Nine  Hundred 
Twenty Only) to 60,66,10,420 Equity Shares of  Rs. 1 each aggregating   Rs. 
60,66,10,420 (Rupees Sixty Crore Sixty Six Lakhs Ten Thousand Four  Hundred 
Twenty Only).

7.  Public Deposits and Loans/Advances

Your  Company  has  not  accepted any deposits  from  the  public,  or  its 
employees during the year under review.

Pursuant  to  Clause  32  of the  Listing  Agreement,  the  particulars  of 
loans/advances  given  to subsidiaries have been disclosed  in  the  Annual 
Accounts of the Company.

8  Employee Stock Option Scheme (ESOP)

As  on March 31, 2012, 64,62,960 stock options are outstanding  (comprising 
vested and unvested, after adjustment for lapsed and exercised options), in 
aggregate, for exercise as per the exercise schedule and are exercisable at 
a price of  Rs. 52.03 per stock option.

Each  option, when exercised, as per the exercise schedule,  would  entitle 
the  holder to subscribe for one equity share of the Company of face  value  
Rs. 1 each.

During the year under review, 15,46,950 options got vested to the employees 
of  the Company and in aggregate, 48,64,730 options stands vested with  the 
employees  as on March 31, 2012. Further during the year,  77,500  options, 
were  exercised  by the optionees at an exercise price of   Rs.  21.70  and 
accordingly the Company has allotted 77,500 Equity Shares, in aggregate, of 
face value  Rs. 1 each to the respective employees.

The  particulars with regard to the Employee Stock Options as on March  31, 
2012 as required to be disclosed pursuant to the provisions of Clause 12 of 
SEBI  (Employee  Stock Option Scheme and Employee  Stock  Purchase  Scheme) 
Guidelines 1999, as amended, are set out in Annexure I to this Report.

9. Status of GDSs

During the financial year 2005-06, the Company had issued Global Depository 
Shares  (GDSs)  and  the underlying shares against each of  the  GDSs  were 
issued in the name of the Depository, Citi Bank N.A.

As  on March 31, 2012, 1,20,720 GDSs have remained outstanding which  forms 
part of the existing paid up capital of the Company.

10. Consolidated Financial Statements

The Consolidated Financial Statements of the Company prepared in accordance 
with applicable Accounting Standards forms a part of this Annual Report.

11. Corporate Governance

As  per  Clause  49 of the Listing Agreement with the  Stock  Exchanges,  a 
separate Chapter on Corporate Governance practices followed by the  Company 
together  with  a  Certificate  from  the  Company`s  Auditors   confirming 
compliance forms part of this Report.

12. Directors

In  accordance  with  Article  135 and Article  186A  of  the  Articles  of 
Association, on October 21, 2011, the Board of Directors appointed Dr.  Ila 
Patnaik as an Additional Director of the Company.

The  Company has received a Notice under Section 257 of the Companies  Act, 
1956 from a member signifying his intention to propose Dr. Ila Patnaik as a 
candidate  for  the office of Director at the  forthcoming  Annual  General 
Meeting.

As  per the provisions of the Companies Act, 1956 read with Article 152  of 
the  Articles  of Association of the Company, Prof. Fred  Moavenzadeh,  Mr. 
Rajas  R.  Doshi and Mr. D. M. Popat are the Directors of the  Company  who 
retire by rotation and being eligible, offer themselves for re-appointment.

The  Company  has received Form DD-A from all these Directors  as  required 
under  the Companies (Disqualification of Directors under Section  274  (1) 
(g) of the Companies Act, 1956) Rules, 2003.

A  brief  profile  of  all these  Directors  containing  details  of  their 
qualifications, expertise, other directorships, committee memberships  etc. 
has been given in the Report on the Corporate Governance as well as in  the 
Notice of the ensuing Annual General Meeting of the Company.

13. Directors` Responsibility Statement

In accordance with the provisions of Section 217(2AA) of the Companies Act, 
1956, your Directors confirm that:

a)  in  the preparation of the annual accounts, the  applicable  accounting 
standards have been followed and there has been no material departure;

b)  the  selected  accounting policies were applied  consistently  and  the 
Directors  made judgments and estimates that are reasonable and prudent  so 
as  to give a true and fair view of the state of affairs of the Company  as 
at March 31, 2012 and of the loss of the Company for the year ended on that 
date.

c)  proper  and  sufficient  care has been taken  for  the  maintenance  of 
adequate  accounting  records  in accordance with  the  provisions  of  the 
Companies  Act,1956  for  safeguarding the assets of the  Company  and  for 
preventing and detecting fraud and other irregularities.

d) the annual accounts have been prepared on a going concern basis.

14. Industrial Relations

The industrial relations continued to be generally peaceful and cordial.

15. Transfer to Investor Education and Protection Fund (IEPF)

The  Company has, during the year under review, transferred a sum  of   Rs. 
7,03,275 to Investor Education and Protection Fund, in compliance with  the 
provisions  of  Section 205C of the Companies Act, 1956.  The  said  amount 
represents  dividend for the year 2003-04 which remained unclaimed  by  the 
shareholders  of  the Company for a period exceeding 7 years from  its  due 
date of payment.

16. Particulars of Employees and other additional information.

The  information required under Section 217(2A) of the Companies Act,  1956 
and the Rules made there under is given in the Annexure to this Report  and 
forms part of the Report. However, in terms of Section 219(1)(b)(iv) of the 
Companies  Act,  1956,  the  Report and Accounts  are  being  sent  to  the 
shareholders  excluding the aforesaid Annexure. Any Shareholder  interested 
in  obtaining  copy of the same may write to the Company Secretary  at  the 
Registered Office of the Company.

17.  Conservation  of Energy, Technology Absorption  and  Foreign  Exchange 
Earnings and Outgo.

The  information  relating  to  the  conservation  of  energy,   technology 
absorption  and  foreign  exchange earnings and outgo  as  required  to  be 
disclosed  under the Companies (Disclosure of Particulars in the Report  of 
the Board of Directors) Rules 1988, is given in Annexure II forming part of 
this Report.

18. Auditors

M/s  K.  S.  Aiyar & Co., Chartered Accountants, Mumbai,  Auditors  of  the 
Company, bearing ICAI Registration No. 100186W retire at the ensuing Annual 
General Meeting and are eligible for re-appointment.

As  required under the provisions of section 224(1B) of the Companies  Act, 
1956,  the Company has obtained a written certificate from the Auditors  to 
the effect that their re-appointment, if made, would be in conformity  with 
the limits specified in the said section.

19. Auditors` Report

The Auditors` Report to the shareholders on the Accounts of the Company for 
the financial year ended March 31, 2012 does not contain any qualification.

20. Acknowledgements

Your Directors would like to acknowledge and place on record their  sincere 
appreciation  to all stakeholders -Clients, Financial Institutions,  Banks, 
Central and State Governments, the Company`s valued investors and all other 
business  partners for their continued co-operation and  excellent  support 
received during the year.

Your  Directors recognize and appreciate the efforts and hard work  of  all 
the  employees  of  the Company and their  continued  contribution  to  its 
progress.

                                   For and on behalf of Board of Directors,

                                   AJIT GULABCHAND
                                   Chairman & Managing Director
Registered Office:

Hincon House, 11th Floor,
247 Park, Lal Bahadur Shastri 
Marg Vikhroli (West) 
Mumbai 400 083

Place: Mumbai
Date : April 27, 2012

Annexure I to the Directors` Report:

Disclosure  pursuant to the provisions of Securities and Exchange Board  of 
India,  (Employee Stock Option Scheme and Employee Stock  Purchase  Scheme) 
Guidelines, 1999 ("SEBI Guidelines") as at March 31, 2012:

No. Particulars                    Details

a) Options granted                 93,05,100 Options 

b) Pricing Formula                 For Options in force

                                   No. of Options      Exercise Price

                                   64,62,960           52.03

                                   Pricing formula for remaining Options:

                                   The closing market price on the Stock 
                                   Exchange, which recorded the highest 
                                   trading volume in the Company`s share 
                                   prior to the date of the Meeting of 
                                   ESOP Compensation Committee in which 
                                   Options were granted. 

c) Options vested                  48,64,730 

d) Options exercised               1,04,360 

e) Total No. of shares arising as 
a result of exercise of Options    1,04,360

f) Options lapsed                  18,32,740 

g) Variation of terms of Options   In accordance with the approval of the 
                                   Board of Directors of the Company, the 
                                   ESOP Compensation Committee had during 
                                   FY 2009-10 re-priced 41,31,600 Options 
                                   granted by the Company at Rs.104.05 per
                                   Stock Option (Earlier Rs.132.50 per
                                   Stock Option) 

h) Money realized by exercise 
of Options                         Rs.34,36,133 

j) Total No. of Options in force   64,62,960 

j) Diluted Earnings Per Share      Diluted EPS  before and after 
(EPS) pursuant to issue of         extraordinary items  Rs. (3.62)
shares on exercise of Options 
calculated in accordance with 
AS 20  

k) The difference between the      The difference between the employee 
employee compensation cost         compensation cost computed using the 
computed using the intrinsic       intrinsic value of stock options and the
value of stock  options and        employee compensation cost that shall 
the employee compensation          have been recognized if the Company had
cost that shall have been          used the fair value of the options is
recognized if the Company          Rs.96,82,044. 
had used the fair value of 
the options.  

l) Impact of Difference on Net     Had fair value method been adopted for 
Profits and EPS of the Company     expensing the ESOP compensation:

                                   (a) Loss after tax would have been 
                                   higher by Rs.0.97 crore.

                                   (b) Basic  EPS before and after 
                                   extraordinary items would have decreased 
                                   from Rs.(3.66) per share to Rs.(3.68) 
                                   per share

                                   (c) Diluted EPS before and after 
                                   extraordinary items would have decreased
                                   from Rs.(3.62) per share to Rs.(3.64) 
                                   per share

m) Method used to estimate the     Forward start Options together with 
fair value                         Black Scholes option pricing method 

n) Weighted Average inputs used 
in the valuation model

* Risk Free Interest Rate          6.416%

* Expected Life during vesting     2 years
period 

* Expected Volatility              60%

* Expected Dividends per share     Rs.0.70

* Price of underlying shares 
at grant date

- For Options granted on 
April 25, 2008                     Rs.104.05

- For Options granted on           
October 23, 2008                   Rs.43.40 

o) Weighted Average Exercise 
Price of Options

- For Options granted on 
April 25, 2008                     Rs.104.05  

- For Options granted on 
October 23, 2008                   Rs.43.40 

p) Weighted Average Fair value 
of Options whose exercise price  
equals to the market price of 
the shares on the date of the 
grant.

- For Options granted on April 
25, 2008                           Rs.36.80

- For Options granted on 
October 23, 2008                   Rs.15.82 

q) Total Fair Value of options 
whose exercise price               Rs.126,539,915
equals to the market price of 
the shares on the date             No options are granted at prices higher
of the grant.                      or lower than market prices. 

Employee wise details of Options granted and in force:

Directors & Senior Managerial Personnel                   Number of Options 
Name                          Designation                    granted and in 
                                                                      force

1. Mr. Y.H. Malegam           Director                               68,600 

2. Mr. Rajas R. Doshi         Director                               68,600 

3. Mr. D. M. Popat            Director                               68,600 

4. Mr. Ram P Gandhi           Director                               68,600 

5. Prof. Fred Moavenzadeh     Director                               68,600

6. Mr. Sharad M. Kulkarni     Director                               48,600

7. Mr. Nirmal P Bhogilal      Director                               68,600 

8. Mr. Anil Singhvi           Director                               54,880 

9. Mr. Arun V. Karambelkar*   President & 
                              Whole-time Director                  5,49,000 
10. Mr. Rajgopal Nogja        Group President - 
                              Development Companies                3,43,200

11. Mr. Praveen  Sood*        Group Chief Financial Officer-       5,49,000
                              Executive Vice President - 
                              HCC Group Office

12. Mr. Aditya Jain Group     Executive Vice President-
                              Human Resources                      4,00,600 

13. Mr. Pervez Alam*          Chief Commercial Officer             6,86,400 

14. Mr. N.R. Acharyulu*       Chief Operating Officer - 
                              HCC E&C                              6,86,400 

15. Mr. S.K. Dharmadhikari    Executive Vice President - 
                              BD & CS                              3,08,880 

16. Mr. D.M. Kudtarkar*       Chief Technology Officer             6,86,400 

17. Mr. V.P Kulkarni          Company Secretary                    2,74,400 

18. Mr. K.R. Visvanath*       Vice President - Nuclear,  
                              Thermal, Special Projects            4,57,400
                              & Water  

19. Mr. Satish Pendse         President - Highbar Technologies     2,74,400

20. Mr. Jimmy Mogal           Vice President -Corporate            2,74,400
                              Communications 

21. Mr. S.W. Gaitonde*        Vice President                       4,57,400

Total No. of Options Outstanding                                  64,62,960 

Identified  employees who were granted Options, during any one year,  equal 
to  or  exceeding 1% of the issued capital of the Company at  the  time  of 
grant: Nil

*  Employees  who had been granted Options amounting to 5% or more  of  the 
total Options granted.

                              For and on behalf of the Board of Directors


                              AJIT GULABCHAND
                              Chairman & Managing Director

Registered Office:

Hincon House, 11th Floor,
247, Park, Lal Bahadur Shastri Marg 
Vikhroli (West) Mumbai-400 083

Place: Mumbai
Dated: April 27, 2012

Annexure II to the Directors` Report:

Information  as per section 217(1)(e) of the Companies Act, 1956 read  with 
the  Companies  (Disclosure of particulars in the Report of  the  Board  of 
Directors) Rules, 1988 for the financial year ended March 31, 2012.

I. Conservation of Energy

a) Energy Conservation Measures Taken:

* Your Company is continuing with energy saving measures initiated  earlier 
like  usage  of Load Sharing System in D.G. plants, APFC  (Automatic  Power 
Factor  Controller) panels for GRID Power, FCMA (Flux Compensated  Magnetic 
Amplifier)  Starter  for  Crusher Motors, Variable  Frequency  Drive  (VFD) 
Starting System for Ventilation Fans & EOT / Gantry Cranes.

*  Use of Solar Water Heating System at Nimoo Bazgo Project  which  reduces 
the power requirement.

*  Hot  Water  Generators have been procured and  are  being  installed  at 
Kishanganga for supplying hot water to Camp. It uses the Waste Heat in  the 
Jacket Water of Diesel Generator Sets.

b)  Additional  investment  and proposals, if  any  being  implemented  for 
reduction in consumption of Energy:

Introduction  of  Lighting Energy Saver (About 10 %) in  Power  circuit  at 
Project sites Locations like Camp, Office, Yard & Area Lighting etc.

Reuse  of recycled water for Crushing Plant operation. This avoids  pumping 
of water from the source located at a distance.

c)  Impact  of  measures  at (a) and (b)  above  for  reduction  of  Energy 
consumption and consequent impact on the production of goods:

Energy  conservation  measures continue to reduce the production  cost  per 
unit with reference to energy consumption.

Reuse of recycled water for Crushing Plant operation reduces the production 
cost in addition to conservation of water resource.

d)  Total energy consumption and energy consumption per unit as per form  A 
of Annexure to the rules of Industries specified in the schedule thereto:

Not Applicable

II. Technology Absorption

Efforts made in technology absorption as per Form-B of the Annexure to  the 
Rules.

1.  Research and Development (R&D)

Applied research and development mostly aims at cost optimization, but in a 
highly competitive market, strategically building sustainable and  holistic 
competitiveness  requires  much more than cost optimization.  Moreover  the 
complex nature and changing stipulations of recent contracts are  demanding 
a  fresh  paradigm  shift  at the way contracts  are  being  executed.  The 
objective  of  the R&D efforts is to specifically assist  and  promote  all 
those  activities  which  help  projects  to  be  executed  with   enhanced 
efficiency  and improved level of quality. While  collaborating  internally 
with  the  construction  sites  and  externally  with  various   suppliers, 
manufacturers,  organizations  and academia, the research  and  development 
projects are aimed at faster penetration in to multiple sites and  building 
a sustainable knowledge and skill base.

A sampling of few of R&D efforts is presented below:

i. Alternative pavement designs for enhanced life and reduced  maintenance. 
This includes designs with

a. Polymer stabilized pavement foundation with increased strength

b. Cementitious stabilizers in expansive soils

c. Geocells to reduce pavement thickness and make it sustainable

d. Anti-rutting agents used in bitumen layers

ii.  Use of statistical methods for improving and optimizing  concrete  and 
shotcrete mix proportioning

iii. Use of cloth fabric to improve the finishibility of concrete

iv. Use of self consolidating concrete

v. Optimizing labor cost through process improvement

vi. Pavement embankment slope reduction using geogrids

vii.   Improvement   in  project  planning  and  management   for   project 
acceleration

viii. Changes in the placement methods of dam concrete

Training  is  an  important part of the  developmental  efforts  and  R&D`s 
invests attempts at expanding it beyond organizational boundaries.  Efforts 
are  persistently  invested  in brining the skill  levels  of  construction 
engineers and designers. Last year, for example, in an effort to  introduce 
new design concept for tunnel waterproofing, R&D in collaboration with BASF 
construction  chemicals organized a one day designers` workshop  for  HCC`s 
designers,  including external design firms whom HCC engages on  a  routine 
basis.

The  academic  dialogue continually takes place to facilitate the  flow  of 
fresh  knowledge  and explore avenues of getting  involved  with  happening 
research on educational campuses. With regard to the international efforts, 
your  Company  has signed up for a membership under  the  industry  liaison 
program  (ILP) with the Massachusetts Institute of Technology  (MIT),  USA. 
This  agreement is helping your Company foresee some of the emerging  areas 
of  construction  and engineering technology including  materials,  energy, 
etc.

The Company has spent  Rs. 0.12 crore towards Research and Development.

2. Technology Absorption, Adaptation & Innovation

a)  Efforts made towards technology absorption, adaptation  and  innovation 
during the year 2011-12 are:

*  For  Kishanganga  Hydroelectric project, proposal  for  adopting  double 
shield  type  of  Tunnel boring machine has been mobilized  at  site.  This 
machine  has  advantages of overcoming adverse  geological  challenges  and 
continuous segment erection.

* For Kishanganga Hydroelectric project, proposal for adoption of  Concrete 
face  rockfill dam [CFRD] has been finalized which has got cost  advantages 
over  conventional concrete dams. For the foundation, plastic cut off  wall 
is being adopted.

*  For Nimoo Bazgo Hydroelectric project, concreting was done in  extremely 
cold  temperatures  by providing thermal blanket to  concrete  surface  for 
overcoming  temperature drop effect. For concrete, special admixtures  were 
used  to  achieve  the desired setting within the  allowable  time  in  the 
extreme cold temperatures.

* For Nimoo Bazgo & Chutak Hydroelectric project, aviation turbine fuel was 
used as an additive in fuel for equipments working in high altitude.

*  For  Vizag  and  Padur  Underground  Cavern  excavation  in  rock,  bulk 
underground  liquid  explosives were used for blasting  which  resulted  in 
reduction  in time cycle and better yield. By adopting this  technique  and 
modifications  in  sequence of excavation, record hard rock  excavation  of 
1,00,000  cum/month was achieved. The analysis and design of  Rock  Caverns 
was  done  by  three dimensional modeling of entire rock  medium  with  the 
Caverns  and rock supports designed using UnWedge analysis  using  software 
code UNWEDGE.

* For Narmada Canal Package 25 Project, Pipeline design was optimized using 
specialist  software  SAP  2.0  developed  by  IISc,  Bangalore,  which  is 
internationally  acclaimed. This enabled us to design the  system  in-house 
for  transient loads and procure the surge control tools /  products  from. 
The system has been approved by GWIL.

*  For  Katch  Branch  canal  II as the project  site  is  located  in  the 
seismically  most active zone, viz. zone V, the canal embankments run  upto 
heights  as  high  as 9m. As a matter of abundant precaution  and  also  to 
arrive  at the most optimum design, specialist services of IIT Bombay  were 
requisitioned. IIT used some of the most advanced softwares, viz.  SLOPE/W, 
SEEP/W and FLAC for the dynamic analysis of these embankments. This ensured 
optimization apart from accuracy in the analysis. It is being well received 
by SSNNL,

*  For  Dagachu Hydroelectric project, in order to speed  up  construction, 
raise  boring machine for excavation of pilot hole for surge shaft and  for 
excavation  of full cross section of pressure shaft has been mobilized.  In 
order  to  accelerate  tunneling  progress, use of  ITC  tunnel  loader  in 
combination   with   reversible  dumper  has  been   adopted   for   tunnel 
construction.

*  For Dagachu Hydroelectric project, the design and drawings were  carried 
out  by using following softwares in association with our  consultants  M/S 
SNC   lavalin  India  for  optimizing  the  design  for   various   project 
components:> Swedge-Used for design of open excavations and slope stability 
of tunnel portals.

>   Phase-2-Finite  Element  Model  based  software  used  for  design   of 
underground  tunnels  and Power house Cavern. Helped to optimize  the  rock 
support requirements.

> GeoSlope-Used for design of unstable area through which Head Race Channel 
of the project.

* For Tehri Pumped storage project in association with M/S EDF France,  our 
design  consultants have carried out the project design and drawings  using 
the   following  softwares  for  achieving  optimization  of  the   various 
underground  structures:>  Flac  3D-The  software is  being  used  for  the 
analysis of the support requirements for the Underground Power House.

>  Minedw-A 3 D hydraulic model of the Tehri PSP area is being built  using 
this model.

*  For  Sainj  Hydroelectric project in association with  M/S  AF  Colenco, 
Switzerland, our design consultants have carried out the project design and 
drawings  using following softwares for achieving optimization  of  various 
structures.

> FENAS & REMI ( Refraction Micro Tremor) software is being adopted for the 
design of the Barrage.

*  Double  Shield Tunnel Boring Machine (TBM) is being  used  at  Veligonda 
project  for  excavating  large  diameter  very  long  water  tunnel,  with 
continuous  conveyor for mucking and simultaneous installation  of  precast 
segmental lining.

* New Austrian Tunneling Method (NATM) is being used at Pir Panjal  tunnels 
in Jammu and Kashmir using Tunnel Version excavators and Road Headers.

*  For  NH34  pavement construction project, chemical  and  bio-based  soil 
stabilization  methods are considered. This will also include use  of  soil 
stabilizing machineries for improved quality control.

*  For some stretches of NH34 pavement, alternative pavement designs  using 
international standards and codes are being proposed.

*   A proposal for installing min-hydro power plants to generate  power  to 
cater to the needs of site establishments is under consideration.

*   Automation  of equipments foundation designs for  different  foundation 
conditions by integration of Excel and AutoCAD

b) Benefits derived as a result of the above efforts:

Reduction in cycle time of construction of different components and thereby 
increasing   of   productivity.  Eco  friendly  design   and   construction 
implementation and energy conservation.

The  utilisation  of above various softwares in design  of  structures  has 
resulted  in  the optimisation of design component of  the  structures  and 
resulted into reduction of construction costs.

Development  of  Human Resource in use of advanced technology  with  modern 
equipment and technology.

c) Technology                 Year of   Has technology 
Imported                      Import    been fully absorbed

Use of Geo textile            2007      Absorbed 
bags replacing boulder 
crate pitching for Teesta 
Diversion scheme

Use of Fly ash for            2008      Absorbed 
embankment and RE wall 
backfilling

Orica Emulsion base           2008      Absorbed  
explosive & Powerdet long  
delay detonators

Roller Compacted              2008      Under Implementation 
Concrete Technology at  
Teesta Project

Wassara drilling              2008      Absorbed
Equipment (unique
Method of drilling
by using water power)

Cold weather                  2008      Absorbed
Concreting system and 
Protection works when  
Atmospheric temperature  
is below 5 C

Construction of cable         2009      Absorbed
stayed bridge using 
Cantilever gantry

Construction of surge         2010      Under
shaft using raise boring                Implementation
machine

Construction of tunnel        2009      Under
using NATM                              Implementation
Method

Construction of tunnel        2011      Under
using double shield                     Implementation
Tunnel boring machine

Technology for                2011      Under
construction of                         Implementation 
concrete faced 
rockfill dam

Construction of               2011      Under
dry dock by using                       Implementation 
precast cum floating 
caissons.

Innovation

Your Company has created a innovation Forum and dedicated Innovation Portal 
for collecting and working on new ideas generated within the  organization. 
New  ideas related to ongoing projects as well as ideas related  to  energy 
saving,  water saving and reduction in environmental damages are  collected 
from  all the employees either through portal or by direct  interaction  by 
highly  motivated  approach.  The  collected  ideas  are  shortlisted   and 
evaluated by Structured Evaluation Process. Specific tasks are  implemented 
at  the  project  sites.  Experiences gained  from  one  project  are  then 
selectively applied to other project sites.

Some of the innovation ideas and focus areas for this year are as follows:

i. Replacement of natural sand with air classified crushed and

ii.  Improving  adverse geological / subsoil condition.  The  geological  / 
subsoil  condition been improved by adopting innovative alternative  method 
like stone columns, chemical grouting, steel liner support etc.

iii.  Reduction in natural resources by environmentally sustainable  (Green 
Technology) materials/ technologies; e.g. Use of EROSION CONTROL

COIR BLANKETS replacing stone pitching.

III. Foreign Exchange earnings and outgo:

(a)  Activities relating to exports, initiative taken to increase  exports, 
development  of  new  export market development of new  export  market  for 
production services and export plans:

Visits  are being made by technical and marketing personnel to develop  new 
export markets from time to time.

(b) Total Foreign Exchange used and earned:

The information on Foreign Exchange earnings and outgo is contained in Note 
no. 38 forming part of the accounts.

                              For and on behalf of the Board of Directors

                              AJIT GULABCHAND
                              Chairman & Managing Director

Registered Office:

Hincon House, 11th Floor,
247 Park, Lal Bahadur 
Shastri Marg Vikhroli (West) 
Mumbai-400 083

Place: Mumbai
Dated: April 27, 2012

Management Discussion and Analysis

Hindustan Construction Company (`HCC` or `the Company`) has been one of the 
pioneering  companies  in  executing  large  scale  infrastructure  related 
construction  projects in India. It has undertaken some of the largest  and 
most  technically challenging projects that have been part of the  progress 
of  India`s overall physical infrastructure. By investing in state  of  the 
art  equipments, adopting world class operational processes which has  lead 
to  an  immaculate execution and by maintaining the  highest  standards  of 
health  &  safety, HCC has established itself as an  industry  leader.  HCC 
continues  to  promote  responsible  infrastructure  development  and   its 
evolution  has been intrinsically linked to the progress of  infrastructure 
development, in the country.

The infrastructure development story in India has been plagued with  issues 
of  implementation.  As a result, the pace of growth has simply  been  much 
slower  than  the  needs of an economy intending to  maintain  a  sustained 
growth  rate of close to 9%. And in 2011-12, there has been a  considerable 
slowdown in development in the infrastructure sector.

Clearly,  there is sufficient latent demand for large scale  infrastructure 
development  across different sectors ranging from power to  transportation 
to urban infrastructure.

Infrastructure and Construction - the long term opportunity

The  Planning  Commission`s  XIth Five-Year  Plan  (20072012)  had  already 
identified  that  inadequate infrastructure was a major constraint  on  the 
country`s  rapid growth. The Plan had, therefore, emphasized the  need  for 
massive expansion in investment in infrastructure based on a combination of 
public and private investment, the latter through various forms of  public-
private partnerships (PPP). In the last few years, substantial progress has 
been  made in this respect. The total investment in  infrastructure,  which 
includes roads, railways, ports, airports, electricity, telecommunications, 
oil gas pipelines and irrigation, is estimated to have increased from  5.7% 
of GDP in 2007 to around 8.0% by 2012.

The  approach paper to the XIIth Five-Year Plan (20122017) highlights  that 
the  thrust on accelerating the pace of investment in  infrastructure  must 
continue  as this is critical for sustaining and bolstering growth.  Public 
investment  in  infrastructure  will  have to bear  a  large  part  of  the 
infrastructure  needs in backward and remote areas to improve  connectivity 
and expand the much needed public services. Since resource constraints will 
continue to limit public investment in infrastructure in other areas,  PPP-
based development needs to be encouraged wherever feasible. It is necessary 
to  review  the factors which may be constraining private  investment,  and 
take  steps to rectify them. PPP, with appropriate regulation  and  concern 
for equity, should also be encouraged in the social sectors, such as health 
and  education. Several State Governments are already taking steps in  this 
direction.

Considering the critical need of developing infrastructure in the  country, 
construction activities are crucial for creating physical infrastructure in 
the  country. Construction, on an average, accounts for more than  half  of 
the  investment required for setting up critical infrastructure  facilities 
like  power  projects, ports, railways, roads, bridges. Table 1  gives  the 
estimates  of  average construction intensity of  different  infrastructure 
projects.

Table 1: Construction components for various infrastructure projects

                                   Construction 
                                    Intensity%                    

Building                                76 
Mineral Plant                           18
Roads                                   63 
Medium Industry                         20
Bridges                                 65 
Transmission                            22
Urban Infrastructure                    66
Dams                                    75
Power                                   38 
Maintenance                             81
Railways                                78

Source: Planning Commission of India

The  cumulative investment in infrastructure in the Twelfth Five-Year  Plan 
(2012-2017)  is  targeted  at  around $1  trillion.  Nearly  half  of  this 
investment will be channelized into construction projects. Therefore, there 
is considerable long term business scope for players in the  infrastructure 
related large scale construction business. Being an industry leader, HCC is 
always  geared to make the most of this opportunity. However,  while  there 
are always a lot of promises, in the last few years one has observed a wide 
gap   between   economic  need  and  on  ground   implementation   in   the 
infrastructure  industry.  Consequently,  HCC has had  to  reformulate  its 
business  plans  to  deal with challenging ground realities  -  a  business 
environment where an increasing number of players are competing for a  much 
fewer number of projects than what economic realities warrant.

Business Environment - the short term slowdown

The  resilience shown by the Indian economy in 200910 and  2010-11  finally 
gave  way and there has been a significant slowdown in economic  activities 
during  2011-12.  Chart A shows that after two consecutive  years  of  8.4% 
growth,  India`s GDP growth slipped to 6.9% in 2011-12. In line  with  this 
drop in real GDP, construction growth also reduced to 4.8% in 2011-12.

Unfortunately,   the  economic  slowdown  has  been  in   an   inflationary 
environment,  where  the Reserve Bank of India (RBI) has  maintained  tight 
monetary policy leading to high domestic interest rates. Chart B shows that 
the reverse repo rate, which benchmarks the commercial bank`s lending rates 
increased  from 5.75% in April 2011 to 7.5% in March 2012. A year  back  in 
April  2010  it  was only 3.5%. This environment of  slowing  growth,  high 
inflation  and  high interest rates was a complete  dampener  for  investor 
confidence and new capital formation took a further hit.

Typically,  infrastructure  projects have high gestation lags  and  require 
long term financing. The Indian financial system is still evolving in terms 
of  availability of such long term financing instruments. And,  the  global 
economic slowdown has created high levels of uncertainty, which has been  a 
dampener  for capital flows into India, especially for long  term  projects 
like  the ones in the infrastructure sector.  Consequently,  infrastructure 
projects in India are also facing issues on the financing front.

In  addition, several projects that have had financial closure  are  facing 
implementation  problems stemming from issues related to land  acquisition, 
social tensions, environmental problems and administrative delays. Clearly, 
the  pace  of infrastructure development in India is not in sync  with  the 
requirements of a growing economy of its size.

Take the case of two important sectors in the infrastructure space -  power 
and roads. Implementation remains woefully short of planned targets.

* For Power, the eleventh five year plan (2007-2012) had talked of creation 
of 78,700 MWs of new power generation capacity - of which 59,693 MW (75.8%) 
was  thermal power, 15,627 (19.9%) was hydro power and 3,380 MW (4.3%)  was 
nuclear  power.  By  the end of the planning period i.e.  March  31,  2012, 
around 55,000 MWs of total new generation capacity has been put up. This is 
around  70% of what was planned. In addition, many projects that are  under 
implementation  have slowed down due to issues regarding coal linkages  and 
tariff structures.

*  For  Roads, the marquee projects of the National  Highway  Authority  of 
India  (NHAI)  continues to be well behind schedule. Of the 12,109  kms  of 
four-laning  as part of NHDP Phase 3, around 19.5% is yet to be  contracted 
out,  while 52% is under implementation. For the 14,799 kms NHDP  Phase  4, 
contracts are yet to be awarded for 83% of the stretch, while 17% is  under 
implementation.  Similarly, 45% of the 6,500 kms NHDP Phase 5, 100% of  the 
1,000  kms NHDP Phase 6 and 94% of the 700 kms NHDP Phase 7 are yet  to  be 
awarded.  In  addition  to  the fact that  large  parts  of  these  planned 
developments   have  not  yet  been  contracted  out,  there  are   several 
implementation  issues with many of the projects that have been  contracted 
out  on BOT basis. The primary problem stems from issues related with  land 
acquisition.

Performance Highlights

In this backdrop, HCC had entered 2011-12 with a lower order book. While it 
focused on effective execution, the size and structure of the  organisation 
was   geared  for  catering  to  a  much  larger   infrastructure   related 
construction  market. So, the asset base and the fixed cost structure  were 
not in line with the stagnant order book. Consequently, while the  turnover 
remained  at  2010-11 levels, the Company generated losses.  The  financial 
highlights of HCC`s performance on a stand-alone basis in 2011-12 are:

* Order Book is at  Rs. 15336 crore in 2011-12

*  Revenue from operations is at  Rs. 4003 crore in 2011-12 v/s   Rs.  4144 
crore in 2010-11

* EBITDA (before profits from JV, Exceptional item and other income) is  at  
Rs. 443 crore in 2011-12 v/s  Rs. 543.4 crore in 2010-11.

The lower turnover and operating margins in an environment of high interest 
costs  put  severe pressure on the Company`s  profitability.  In  addition, 
further  litigation  and  non payments of  awarded  claims  in  arbitration 
adversely  affected  the Company`s liquidity and  debt  servicing  ability. 
Recognising  this as a problem which cannot be sorted out independently  or 
in  a  short  time frame, HCC approached its bankers with  a  proposal  for 
bilateral  refinancing of the loans with larger tenure. However, there  was 
no  consensus  amongst  the bankers on  this  proposal.  Consequently,  the 
Company  approached its leading bankers and they referred their total  term 
debt  of around  Rs. 3300 crore to the Corporate Debt  Restructuring  (CDR) 
cell. The CDR Empowered Group formally admitted the case for  restructuring 
on  March  29, 2012 by a super majority of lenders . Under  the  regulatory 
frame  work  of the RBI, the CDR forum caters as an official  platform  for 
both  the  creditors  and borrowers to  amicably  and  collectively  evolve 
policies  for working out debt restructuring plans. The broad  contours  of 
this  restructuring  exercise involves re-structuring of debt in  terms  of 
payback  period,  deferring certain interests on term  loans,  concessional 
rate  of interest and provision of further need based working  capital  and 
loans for capacity expansion. This debt restructuring will provide HCC with 
breathing space to work on improving operational margins over a period. The 
Company  is  also  raising own funds by liquidating some  of  the  non-core 
assets.  It is expected that the restructured debt, certain amount  of  own 
funds,  tightened cost management and increase in turnover will enable  the 
Company to weather the situation in the medium term.

HCC - Internal Reorientation

In   a  difficult  business  environment,  HCC  has  utilised  2011-12   to 
recalibrate its business. This has been done on several fronts.

First,  given the immense potential that the infrastructure sector  has  in 
India,  HCC had created complete teams for separate verticals that  service 
sectors  within  the engineering and construction business  including  EPC, 
transportation, power, water and industrial. The market potential was large 
enough  to  make each one of these verticals  self  sustaining  businesses. 
However  in  201112  there  were several  unresolved  issues  in  terms  of 
implementation  and a lot to be desired on effective mechanisms of  private 
public  partnerships,  regulatory  environment in  the  country  and  macro 
economic variables. Consequently, it was felt that there is still some time 
before  India`s infrastructure industry translates into a large  market  on 
the  ground  that  could  sustain  each  of  the  Company`s  verticals   as 
independent  businesses.  With this understanding, HCC  undertook  a  major 
organisational restructuring exercise and replaced the verticals  structure 
with a function based organisation system.

Second,  the  Company has been facing a two pronged challenge  in  business 
development  - on one hand, the Company was forced to bid for  projects  at 
very  low margins; while on the other hand, it was regularly losing out  on 
contracts with bids which were not competitive.

Considerable  effort has been spent on revamping the  business  development 
function  to  overcome  this dichotomy. Lot of emphasis has  been  laid  on 
researching  the market to identify projects that are most suitable  for  a 
Company like HCC to pursue.

In addition to this the business development function has been divided into 
lines within the infrastructure space where specific thrust is being  given 
to improve on customer relations. In a related development, the  estimation 
and the business development departments have been integrated to operate as 
a  cohesive  unit.  Through this organisation  structure  a  robust  review 
mechanism has been put in place that focuses on ensuring profitable  growth 
for the Company.

Third, it was observed that HCC had several claims arising out of  disputes 
with  customers.  Many  of these claims are recoverable  and  HCC  is  well 
positioned  to  win legal battles to fructify the claims. In the  last  few 
years, however, this was not considered a core function. On the other hand, 
in  today`s  business environment effective claims management  can  release 
significant  amount  of  cash for the  Company.  Having  identified  claims 
management as an important and core function, the Company has put in  place 
a  team headed by a highly experienced professional who has served  at  HCC 
for  over  3 decades. This team works on getting claims settled up  to  the 
arbitration stage. Most of these claims move from arbitration to the courts 
for  a  full fledged legal process. The Company has  supported  the  claims 
realisation  initiative by establishing a legal team under the  secretarial 
and  legal  department.  This team is actively working on  closure  of  all 
claims cases that have moved from arbitration to a court challenge.  Claims 
management  alone has the potential of raising significant amounts of  cash 
for the Company.

Fourth, the Company has rationalised its work force. This exercise has been 
mainly carried out at the corporate office. This work force rationalisation 
has resulted in the Company operating in a leaner structure.

Business Portfolio

With   a   focus  on  adding  value  across  different  elements   of   the 
infrastructure delivery chain, HCC has evolved from a pure contractor to  a 
construction  major  in India. Today, HCC`s portfolio  comprises  different 
businesses  that have different markets, require different skill  sets  and 
operate under varying risk return profiles. All the different components of 
the  Company`s business are integrated through HCC`s world class  processes 
and value system. The portfolio includes the following diverse yet  related 
businesses.

* Engineering and Construction: This is the Company`s core business,  which 
focuses on transportation, power, water supply and industrial  construction 
projects.   The  business  has  been  extended  to  complete   engineering, 
procurement and construction (EPC) services and in a focused manner the EPC 
part of the business is being strengthened.

*  Total  Services  Contractor: In the last  financial  year,  the  Company 
acquired  Steiner AG (formerly Karl Steiner AG), a leading  Total  Services 
Contractor in Switzerland, which offers its services in Europe and India in 
all facets of real estate development and construction.

*  Infrastructure: This is a move up the infrastructure value  chain  where 
HCC  develops  projects  right  from  planning  and  conceptualisation   to 
execution  and  has  ownership rights on the assets  created.  Returns  are 
generated  from utilisation of the assets and the creation of asset  value. 
Here, the Company is initially focusing on private public partnerships.

*  Real Estate: The real estate business develops commercial &  residential 
property  and is focused to develop state-of-the-art projects. It  is  also 
involved in development of slum rehabilitation projects.

* Integrated Urban Development and Management:

The  focus  area  of this business has been  the  development  of  complete 
integrated  townships.  Today,  HCC is actively pursuing  the  creation  of 
India`s planned hill city in the private sector called Lavasa.

In addition to these businesses, the Company has also extended its internal 
Informational technology (IT) function to form a separate Company - Highbar 
Technologies - that is involved in assisting in improved IT utilisation  in 
the construction industry.

Engineering and Construction Business

The Company`s order backlog as on March 31, 2012 was  Rs. 15,336 crore. The 
order  backlog is well distributed across various sectors including  power, 
transport, water and industrial.

During 2011-12, on the operational front, HCC continued with its  concerted 
efforts at executing projects with lower capital base to improve return  on 
capital. In order to promote this, the Company intensified its  initiatives 
on partnering vendors and increasingly subcontract out non-core  activities 
to them with a view to reduce own capital investment, in different projects 
and thereby release critical working capital.

The developments on the projects front across different sectors in  2011-12 
are given in the following sections.

Power

HCC is a leader in the construction of hydro and nuclear power projects. In 
the  recent  past,  the Company had made a foray  into  the  thermal  power 
segment.

Hydro Power

The  Company  is  involved in the  construction  of  fifteen  hydroelectric 
projects (HEP) for central and state PSUs and private developers. In  2011-
12,  the  Company  completed Chutak HEP for NHPC Ltd  in  Kargil,  Jammu  & 
Kashmir. The project has now been commissioned by NHPC. Chutak HEP won  the 
Construction  India Development Council (CIDC) Vishwakarma award  2012  for 
the best project.

Two other projects Chamera and Uri for NHPC Ltd are at an advanced stage of 
completion.

At  the  3  x 110 MW Kishanganga HEP, which is HCC`s  largest  hydro  power 
project  worth   Rs. 2,725 crore, tunnel boring by a  sophisticated  tunnel 
boring machine is making steady progress.

Two  other projects under implementation in Bhutan - 114 MW Dagachhu  Hydro 
Power Plant and the 1,200 MW Punatsangchhu I HEP are progressing well. Work 
on the Sainj HEP, secured in 2010-11 has also commenced.

In  2011-12,  the  Company secured the contract for  Tehri  Pumped  Storage 
project  along  with  Alstom  Hydro France as  a  consortium  partner.  The 
contract  is  worth  Rs. 1,843 crore and the Company`s share in  the  joint 
venture would be  Rs. 701 crores with a contract period of 54 months.

Nuclear Power

The Company completed civil works of Kudankulam Nuclear Power Project  last 
year.  This project also won the CIDC Vishwakarma award 2012 for  the  best 
project.

The Company secured a  Rs. 888 crore contract for civil works of  Rajasthan 
Atomic  Power  Project  (RAPP) Units 7 & 8 in 2010 - 2011.  Work  is  under 
progress  on  the  foundation  rafts of  the  nuclear  building  and  other 
structures.  A major pour measuring 5,757 cubic metres of concrete for  the 
nuclear  building raft foundation, which is the largest pour at  a  nuclear 
project in India, was successfully completed.

Thermal Power

Contract  for Muzaffarpur Thermal Power Project was secured in  2010  -2011 
from  Kanti Bijlee Utpadan Nigam Limited, a joint venture between NTPC  Ltd 
and  Bihar State Electricity Board (BSEB). The project is  fully  mobilized 
and  works  involving civil and structural erection are  progressing  at  a 
steady pace.

Transportation

The  Company  has  executed several national highway  projects  across  the 
country  since  the launch of the National Highways  Development  Programme 
(NHDP).  In  2011-12,  the  Company  completed  four  contiguous   packages 
aggregating  156 kms of the East West Corridor Lucknow Muzaffarpur  highway 
Project in Uttar Pradesh.

HCC is executing three packages aggregating 256 km of the National  Highway 
NH-34 on Build Operate Transfer (BOT) basis. The project is fully mobilised 
and work is progressing in full swing.

Substructure and superstructure works are underway on the Kolkata  elevated 
corridor  project, which is a 4.23 km long flyover from Park Circus  to  EM 
Bypass.

In  2011-12,  the Company secured two contracts from  North  East  Frontier 
Railway. The first contract worth  Rs. 987 crores is for Bogibeel Rail  cum 
road-bridge  over  the  Brahmaputra River in Assam.  The  project  will  be 
executed  in  joint  venture  with DSD  Bruckenbau  GMBH  Germany  and  VNR 
Infrastructures   Ltd,  Hyderabad,  India.  The  second  contract  is   for 
construction  of 3.3 km long single line BG railway tunnel for New  Railway 
Line Project Jiribam-Tupul (Imphal). The project will be executed in  joint 
venture with Coastal Projects Ltd, Hyderabad, India. The Company is already 
executing two more packages Tunnel 1 & 12 for the same project.

Water Supply and Irrigation

HCC is associated with seven water supply and irrigation projects in Andhra 
Pradesh.  Largest among them is the JCR Devedula Godavari  Lift  Irrigation 
Scheme  where  the  Company  is involved in  all  the  three  phases  under 
implementation.  This is the second largest such water scheme in the  world 
and  it will cater to the irrigation and drinking water requirement  across 
6.47  lakh  acres  of  land.  The first  phase  of  the  project  has  been 
successfully  commissioned,  while  construction of  the  second  phase  is 
nearing completion. In the third phase, HCC is involved in two packages for 
three rows of 38 km pipelines and a 55 km long tunnel.

The Company is engaged in two water supply contracts in Mumbai. One of  the 
contracts - Middle Vaitarna Water Supply Project - involving laying a  15.7 
km  steel  pipeline  was commissioned in March  2012.  The  other  contract 
envisages  construction  of  a 12 km long tunnel about 65  m  below  ground 
level. One section of the tunnel is complete including the concrete lining. 
In  the  second  section, tunnel boring is complete  and  other  works  are 
progressing well.

In  2011-12,  the  Company secured an EPC contract  under  Swarnim  Gujarat 
Saurashtra-Kutch  Water Grid Programme - Package NC 31, from Gujarat  Water 
Infrastructure  Ltd worth  Rs. 289 crore. A similar project  package  NC-25 
for the same client was commissioned in March 2012.

Industrial

The  Company  has been awarded several packages aggregating over   Rs.  850 
crore  for  Aditya  Aluminium  Plant  at  Sambalpur,  Orissa  by   Hindalco 
Industries Ltd. Out of these packages, one package of Potshell  fabrication 
was successfully completed in 2011-12.

The  Company  is executing two underground crude oil  storage  caverns  for 
Indian Strategic Petroleum Reserves Ltd. One is at Vishakhapatnam  (Vizag), 
Andhra Pradesh and the other at Padur, Karnataka. The Vizag cavern is at an 
advanced stage of completion while work at the Padur Cavern is  progressing 
well.

Marine Works

Work on the  Rs. 609 crore contract for reconstruction of the dry dock  and 
wharves in Mumbai for Director General Naval Project is progressing well.

Infrastructure Business

Since   its   inception  in  2008,  HCC  Infrastructure   has   grown   its 
infrastructure  development portfolio to  Rs. 5,500 crore of  assets  under 
management.  These  projects developed through Public  Private  Partnership 
(PPP)  or BOT (Build-Operate-Transfer) mode include six  National  Highways 
Authority of India (NHAI) road concessions, of which three are operational.

HCC Infrastructure follows a disciplined investment strategy that maximizes 
shareholder value by generating stable and rapidly growing streams of  cash 
flow  over  concession periods ranging from 15 to 30  years.  The  Company, 
through  its subsidiaries HCC Concessions and HCC Power, has a  development 
focus  primarily in the roads, water and power sectors. This  is  partially 
due  to the parent Company`s core construction competence in  these  areas, 
having  executed  large projects of national importance across  the  Indian 
sub-continent.  Besides  procuring  a  construction  edge  from  HCC`s  E&C 
division,  HCC Infrastructure has developed a strong management team  whose 
expertise extends from concept innovation and evaluation of risk &  return, 
to  construction  management and operations. Besides focus on  quality  and 
timely  execution, the Company is equally committed to providing  reliable, 
safe  and world class operations and maintenance services to the  country`s 
end users.

Equity Fund Raising Initiative

In  September  2011, HCC Infrastructure raised  Rs. 240 crore  by  diluting 
14.5%  equity  stake in HCC Concessions to The Xander Group  at  an  equity 
valuation of  Rs. 1,650 crore. This pure equity placement, which is  devoid 
of any structured return, and which was completed during challenging market 
conditions,  showcases  both  the  quality  of  the  HCC   Infrastructure`s 
portfolio and the conviction in management team. The Xander Group Inc. is a 
global  investment firm focused on infrastructure, hospitality, retail  and 
real estate sectors. Since 2005, the firm has committed over US$1.8 billion 
of  equity capital to the Indian market across five dedicated India  funds. 
Xander  is  an ideal partner for HCC Infrastructure as  they  have  similar 
traditions with a focus on the long term.

Operational Assets

Dhule Palesner (DPTL) Highway Project (NH3)

The project road achieved provisional completion and toll collection  began 
in  February  2012, four months ahead of its contractual  completion  date. 
This is the third consecutive project that HCC Infrastructure has completed 
significantly ahead of schedule.

This  road  project  (89 km) which is part of  National  Highway  (NH3)  is 
commonly  referred to as the Mumbai-Agra Road. Other stretches of  the  NH3 
are  also under development and additional traffic growth is expected  once 
most  of  the  corridor  is  four-laned. DPTL  is  a  primary  conduit  for 
transportation  of  passengers and freight traffic between major  towns  in 
Maharashtra  and  the state of Madhya Pradesh & Uttar Pradesh  and  largely 
serves industrial traffic.

The  project  is being operated by an in-house operations  and  maintenance 
(O&M)  team.  The concession period is 18 years, including  a  construction 
period  of  30 months. The highway is being developed in  partnership  with 
Sadbhav  Engineering  Ltd  and  John Laing Investments  Ltd  (UK)  with  an 
investment of  Rs. 1,420 crore.

Delhi Faridabad Elevated Expressway (NH2) (dfskyway TM)

The dfskyway TM, commissioned in November 2010, was also completed ahead of 
schedule with an investment of  Rs. 572 crore. The project road is a 4.4 km 
elevated highway connecting Badarpur in Delhi and Faridabad in Haryana. The 
dfskywayT   contributes   significantly  to   Delhi`s   rapidly   expanding 
infrastructure  by  reducing travel time by over 40 minutes  that  benefits 
residents and inter-state traffic alike. It is one of Delhi`s major  radial 
roads  and  caters  to very high traffic volume  of  approximately  100,000 
vehicles  per  day. Designed, engineered and constructed entirely  by  HCC, 
this elevated structure boasts 20 exits, 10 underpasses and is the first of 
its kind spaghetti structure in India. The dfskywayT has won many accolades 
for efficient design and execution, including the Best Project Award by the 
Construction   Industry   Development   Council   (CIDC)   2011   and   the 
Infrastructure Excellence Award 2011 by CNBC TV18.

The National Capital Region has witnessed approximately 20% traffic  growth 
during  the past decade for satellite cities such as Gurgaon and Noida.  In 
the past, the growth of Faridabad was slower due to poor connectivity  with 
the  heart  of  Delhi. With immediate connectivity due  to  dfskywayT,  one 
expects much higher growth for Faridabad, which has recently been cited  as 
the  8th  fastest developing city by The City Mayors  Foundation,  UK.  HCC 
Infrastructure  was  awarded  a  20-year  concession  in  2008  to  design, 
construct and operate this asset by the NHAI.

Nirmal (NBL) Annuity (NH7)

The sole annuity project in the portfolio is the road from Kadtal to  Armur 
in Andhra Pradesh, which forms a part of the Nagpur - Hyderabad section  of 
NH7. This 33 km development was the first investment by the Company and was 
completed 100 days ahead of scheduled completion. The concession period for 
the project is 20 years, including a construction period of 24 months.  The 
project was developed with an investment of  Rs. 315 crore.

Assets under Development

West Bengal (NH34) Highway Project

This  eagerly awaited project being developed by HCC Concessions Ltd  on  a 
Design,  Finance, Build, Operate and Transfer (DFBOT) basis, is  among  the 
largest  PPP  projects in West Bengal (WB). The project road is  the  major 
North-South artery (NH34) which originates at the capital and port city  of 
Kolkata, and ends at Dalkhola in the state of WB, covering a total distance 
of  443.5  km. It is the spine of the transport system in  the  region  and 
provides nearest access to ports (Kolkata and Haldia) for the north eastern 
states of India and neighbouring Bhutan and Nepal. The development of  this 
stretch  will  improve connectivity to the East-West  Corridor,  which  has 
already  been  four-laned. West Bengal is strategically located to  play  a 
pivotal  and catalystic role in promoting economic cooperation in  the  sub 
region (Bangladesh, Bhutan, North Eastern states and West Bengal) which  is 
home to half a billion people.

The  concession lengths for the three different segments totalling  256  km 
range from 25 to 30 years, including a construction period of 30 months and 
an  investment of over  Rs. 3,200 crore. The highway  development,  divided 
into  three  contiguous sections covers Baharampore and Farakka  (103  km), 
Farakka and Raiganj (103 km) & Raiganj

and Dalkhola (50 km).

West  Bengal NSDP grew at a CAGR of 7.4% in the last five years  (FY05-09). 
It  is  the  fourth most populous state in the country  and  is  the  sixth 
largest  contributor to India`s GDP. The traffic on NH34 comprises  of  90% 
commercial  traffic,  carrying a diversified mix  of  manufacturing  goods, 
building  materials, steel, jute, food grains and tea. The  development  of 
this  road  will  give a significant boost to commerce and  trade  in  West 
Bengal  and will help in promoting economic cooperation in south-east  Asia 
sub  region (comprising Bangladesh, Nepal, Bhutan, Eastern India and  North 

Eastern States).

Execution  of  the  project is well underway and has  achieved  nearly  25% 
completion.  Further,  traffic  on the road over the  past  two  years  has 
significantly exceeded expectations.

New Business Opportunities

HCC Infrastructure will continue to evaluate new opportunities, largely  in 
the  areas of HCC`s core construction competence. The Company is  currently 
focussing on a number of PPP opportunities in the Power and Water sectors.

Power

While  2011-12  witnessed the highest capacity addition of 19,459 MW  in  a 
single  year, there has been a slowdown in new investments in  the  thermal 
power  segment,  which is the dominant segment within the power  sector  in 
India. Much of the slowdown is due to issues related to coal linkages. On a 
positive note there has been acceleration in investments in other forms  of 
power,  namely Hydro, Solar and Wind. The Hydro sector has gained  momentum 
in states like J&K, Uttarakhand, Meghalaya, Mizoram, and Maharashtra coming 
up with allotment of hydro power projects through competitive bidding. More 
than  500  MW of Solar projects have been allotted under  various  schemes, 
with  around 300 MW of solar projects already commissioned during  2011-12. 
Further,  more  than 3,000 MW of wind capacity has been added  in  2011-12, 
which is around 5% of total capacity addition in India during the year. The 
demand supply gap in the power sector is still immense. As per the estimate 
of Central Electricity Authority, the energy deficit was 10.3% and the peak 
deficit was 12.9% in 2011-12. The sector is likely to grow at a pace of  7-
8% to sustain the growth of Indian economy.

HCC  Infrastructure`s power team has a wealth of development experience  to 
address  the Company`s entry into the power generation business, where  the 
focus is largely on the Hydro and Renewable Energy sectors. The team,  duly 
supported  by  best  in  class  advisors,  consultants  and  partners,   is 
evaluating  several opportunities in Hydro, Solar and Wind energy.  In  its 
endeavour  to develop power projects, HCC Infrastructure benefits from  the 
extensive  experience and technical expertise of its parent Company HCC  in 
executing  large  and  complex infrastructure  projects  with  world  class 
quality and cost competitiveness.

Water

HCC Infrastructure is also currently evaluating opportunities in the  field 
of  Water Transmission and Treatment. The increase in urban  population  is 
expected  to  put strain on the basic infrastructure, with  water  being  a 
critical requirement both for cooking and sanitation. Urban populations are 
expected  to  grow  40%  by 2021 - we envisage this sector  to  grow  at  a 
significant  pace in the near future and are preparing to  provide  quality 
infrastructure development and services through world-class facilities.

Integrated Urban Development and Management - Lavasa

The focus at Lavasa has always been to establish itself as a distinct  hill 
city,  offering world-class facilities with its own unique features,  where 
one  could  live,  learn, work and play in harmony  with  nature.  As  free 
India`s  planned  hill  city, it offers a wide  range  of  residential  and 
commercial  facilities,  tie-ups with premier, national  and  international 
educational institutions, an extensive range of tourist activities,  family 
entertainment opportunities and several business avenues across a range  of 
industries.

While  operational  progress  was on track,  construction  operations  were 
stalled between November 25, 2010 till November 9, 2011, as the Ministry of 
Environment and Forests (MoEF) had issued `stop-work` notice to the Company 
for alleged violation of Environment Impact Assessment Notification of 1994 
as amended in 2004 and that of 2006. The Company had filed a writ  petition 
in  the Hon`ble Bombay High Court and challenged the show-cause notice  cum 
stop  work  order and the Company`s writ petition  was  admitted.  However, 
while writ petition was pending, in order to save time and to safeguard the 
interests  of the customers and the project at large, HCC  also  approached 
the MoEF for grant of Environment Clearance (EC) to its project. The Expert 
Appraisal Committee (EAC) of MoEF after perusing the documents submitted by 
the  Company, appraised the Company`s project and recommended grant of  the 
EC to the 1st phase of Company`s project comprising 2000 ha.  Consequently, 
MoEF accorded EC to the 1st phase of Company`s project on November 9, 2011. 
Thereafter the work is in progress at the site.

The  project  stoppage,  however, was a dampener to  the  progress  of  the 
project.  And,  one full year of no work due to  environmental  issues  has 
considerably delayed the project. Consequently, the balance sheet of Lavasa 
was  under  pressure.  A  consortium of banks who have  lent  most  of  the 
Company`s   Rs.  850  crore  debt  have  in  principle  agreed  to  a  debt 
restructuring  exercise and an application has been made by the bankers  to 
RBI through use of its special dispensation seeking not to classify  Lavasa 
as a substandard asset.

2011-12 saw several developments at Lavasa.

In  the  hospitality space, Accor Hospitality launched two  of  its  brands 
including  the  Mercure  Lavasa  and  the  1500  plenary  capacity   Lavasa 
International Convention Centre. Novotel and Pullman, also Accor brands are 
in  the  process  of  being built, while Hilton,  Comfort  Inn,  Days  Inn, 
Oakwood,  Jukaso,  Langham Place and Eaton, amongst others, are  slated  to 
follow in quick succession.

On  the  retail  front,  a  significant  area  has  already  been   leased. 
Restaurants like American Diner, Granma`s Homemade Patisserie, Brewberrys -
The Coffee Bar, Chor Bizzare, Subway and Oriental Octopus, Past Times  Pub, 
Tabakh,  Pizzavala, Hungry Hippo and Fruity Bat have commenced  operations. 
State  Bank  of India and Union Bank of India have  already  started  their 
operations in Lavasa.

On  the education front, 2011-12 witnessed the second successful  year  for 
Christel  House Lavasa with a total of 209 students. After the  success  of 
the  first  year, in the year 2011-12, the phase - II  of  `Christel  House 
Lavasa`  was launched. Ecole Hoteliere Lavasa started its third  batch  and 
academic certification from Ecole Hoteliere Lausanne has now been  received 
to conduct Masters programmes and from IGNOU to conduct and award  degrees. 
Next in the pipeline for opening is Mussoorie International Lavasa, powered 
by  Educomp  and EuroKids and Birla Edutech with  primary  and  pre-primary 
schools.  Professional and executive education took off at Lavasa in a  big 
way with Massachusetts Institute of Technology (MIT) having conducted their 
first programme on Airport and Airline Systems, Planning and Management.

My  City  Technology,  a Company promoted by Lavasa,  Cisco  and  Wipro  to 
develop IT infrastructure, also began its operations.

There  was  continuous  stress  on  creating  awareness  through  marketing 
initiatives,  primarily  by exposing the city to a wider  audience  through 
events. A television series called `Urban Longings` was aired to  highlight 
the  need  for  planned new cities. This was supplemented by  a  series  of 
articles by personalities like Dr. APJ Abdul Kalam, who shared their  ideas 
of  a `future city`. Events like `Literature Live` and Lavasa Mifta  Awards 
brought the city closer to arts and culture.

On  the  tourism front, Lavasa has tied up with I-Dream to  create  an  all 
Lavasa  tourism plan including a historical theme park. Lavasa is  also  in 
the process of forging an alliance with EngagePlus - a New Zealand  Company 
for adventure sports activities to offer adventure experience at Dasve  and 
nearby areas.

Lavasa continued its focus on branding and communication activities through 
2011-12.

Importantly, as stated earlier, Lavasa was granted Environmental  Clearance 
by MoEF for the first phase of 2000 Hectares (Ha) in November 2011. A large 
scale  PR exercise across various media channels - print, TV and  online  - 
was undertaken welcoming the news. Social Media and the Lavasa website were 
used to disseminate related information and to address any related queries. 
Media  engagement and relationship building exercise  continued  throughout 
the pre-clearance to post-clearance period. A new brand campaign `At  Work" 
was released in 2012. This was to reassure the general public at large that 
developmental work has begun at Lavasa.

Positive  sales trend continued through the year, with the  Company  giving 
possession to over 150 residential units in Dasve. Residential sales of the 
first  town  Dasve have almost been completed. There have  also  been  many 
enquiries  for  further residential units in Lavasa. Sales for  the  second 
town  Mugaon  was  launched on the occasion of Gudi Padwa  in  March  2012. 
Almost  75% of the inventory has been sold out within just a  fortnight  of 
the launch. It is also heartening to know that there have been less than 1% 
cancellation  requests from customers in spite of the MoEF status quo.  The 
current  database  of enquiries for the purchase of apartments  and  villas 
exceeded almost eighty thousand, which indicates a healthy demand.

Institutional  sales and commercial tie ups have also made progress with  a 
number of MoUs being signed. Land sale has been made to State Bank of India 
which  is planning to set up a retail bank and a training centre cum  guest 
house at Dasve. Development of an integrated Corporate Training Centre with 
a residential component at Mugaon is also being planned by a consortium led 
by the Giria Investment Corporation, Bengaluru. The Art of Living centre is 
also  slated  to  open at Mugaon. Sales are also fast  picking  up  in  our 
commercial  office spaces ventures - 247 Business Square and  247  Business 
Avenue at Lavasa. These are just initial steps towards a 365 day - 247 city 
that  Lavasa is working towards. In the next year, the target is  for  many 
such industries including IT and ITES, Biotechnology, Knowledge Parks,  R&D 
centres  and  Corporate Training centres to enable permanent  residents  to 
move in.

Real Estate

HCC Real Estate Ltd (HREL), a wholly owned subsidiary of your Company,  has 
inherent skills and resources to develop and deliver high value real estate 
projects  that  helps in building sustained communities across  India.  The 
focus  is to develop `state-of-the-art` projects which would provide  world 
class  quality,  engineering  and  technology and  create  a  unique  value 
proposition for the customers.

247Park  II  at Vikhroli (West): The Company has initiated the  process  of 
obtaining approvals for development of commercial office building  adjacent 
to  247Park  I  which is expected to have  commercial  office  premises  of 
approx.  400,000  sq  ft of saleable  area  under  "Public-Parking  Policy" 
finalised  by Municipal Corporation of Greater Mumbai (MCGM).  The  Company 
has  received  preliminary  approvals  from  Jt.  Commissioner-Traffic  for 
parking  of  520  cars.  The  Company  envisages  the  completion  of   the 
construction of the project by 2014. The marketing and sales department  of 
the  Company  has submitted Request for Proposals (RFP)  for  built-to-suit 
(BTS) commercial space requirement and the Company is hopeful of  receiving 
good response riding on the sucess of 247Park Phase I.

Development of Vikhroli (E) land parcel: HCC owns a land parcel at Hariyali 
village,   Vikhroli  (E),  which  was  declared  a  slum  under  the   Slum 
Rehabilitation  Act of 1973. HCC Real Estate is proposing to  develop  this 
land  parcel through Panchkutir Developers Ltd., a wholly owned  subsidiary 
of  HCC. Consent has been received from more than 70% of slum dwellers  for 
development  of this land, and the necessary documentation has  been  filed 
with the statutory authorities seeking an approval for development on  this 
land parcel.

Charosa  Wineries  Limited:  Your Company`s step  down  subsidiary  Charosa 
Wineries Limited has till date purchased about 211 acres of land.  Purchase 
of  another  27 acres of land is in progress as on date.  Total  land  area 
under  cultivation  is 81acres. During the year, the Company signed  a  PMC 
agreement  with the Project Management Team of HREL for  providing  project 
management,  health-safety  and  environment  management.  Construction  of 
Winery  Building  is at an advanced stage.The Company has  been  accredited 
under  "Mahabhraman" scheme of Maharashtra Tourism Development  Corporation 
(MTDC)  to operate tour packages within the state of Maharashtra.  Further, 
the  Company has obtained registration from MTDC as a service provider  for 
tourism.

Internationally  renowned  Master Planners and Architects,  HOK  have  done 
master  planning for setting up wine tourism project consisting of  tourist 
resorts, cellar-doors, wine bars, restaurant, theme park, adventure sports, 
amphitheater, Wine spa etc. Harvesting and crushing of nearly 200 MT grapes 
has been completed during the year & the Company expects to launch the wine 
in the market during financial year 2012-13. During the year, Company fully 
repaid the loan taken from the bankers.

Steiner AG (formerly Karl Steiner AG), Switzerland Steiner AG is a  leading 

general   contracting  Company  in  Switzerland,  specialized  in   turnkey 
development of new buildings and refurbishments, and offers services in all 
facets  of  real estate development and construction.  Through  its  wholly 
owned  subsidiary  HCC Mauritius Enterprises Limited, HCC owns  a  majority 
stake of 66% in Steiner AG.

In  June  2011, Steiner AG moved into its new headquarters located  in  the 
Andreaspark Business Centre in Zurich, which were developed and realized by 
Steiner  AG  itself.  On this occasion, the Company`s  corporate  name  was 
changed  from  "Karl Steiner AG (Karl Steiner SA) (Karl  Steiner  Ltd)"  to 
"Steiner AG (Steiner SA) (Steiner Ltd)".

Following through on HCC`s aim of accessing Steiner AG`s rich experience of 
constructing   world-class  integrated  buildings,  Steiner  AG   initiated 
international operations by

incorporating a wholly owned subsidiary, Steiner India Ltd, in August 2011. 
It  has its registered office in Mumbai and pursues the main  objective  of 
undertaking construction of real estate projects in India.

Steiner  AG  generated  a  revenue of CHF 728  million  (12  month  period) 
compared  to  CHF 597 million in the 11 month period in the  last  business 
year. The profit before tax amounted to CHF 4.0 million in FY 2011-12.

In  the business year 2011-12 Steiner AG signed many  important  contracts, 
which  include  the  project NeueSchanzenpost/PostParc in  Berne,  a  total 
services  contract  of around CHF 160 million with Swiss Post  as  client,a 
general contract for the project MehralsWohnen in Zurich, consisting of  13 
apartment buildings and a range of office spaces and business premises, for 
a total volume of around CHF 145 million and a total services contract  for 
project  Lindbergh  in Zurich, a large-scale building for  mixed  use  with 
Credit Suisse as investor with a total volume of around CHF 100 million.

At year end, the order backlog of Steiner AG was CHF 1,512 million compared 
to  CHF  1,018 million as of March 31, 2011. Steiner AG  has  also  secured 
projects worth CHF 135 million which are yet to be signed.

Highbar Technologies

To  leverage the expertise developed in providing in-house IT services  and 
cater  to the IT needs of the construction industry, on April 1, 2010,  HCC 
hived  off  its  IT  department into  a  separate  Company  called  Highbar 
Technologies.  The core team comprises IT and infrastructure  professionals 
who  have amalgamated the legacy of domain knowledge in the  infrastructure 
business with information technology. Highbar focuses on IT  implementation 
initiatives   from  a  business  transformation  perspective  rather   than 
technology implementation perspective.

In its very second year of operations, Highbar was able to compete  against 
well-established industry players to serve 10 new customers. With this, the 
total customer base increased to 50. A long list of reference customers and 
high  quantum of repeat business indicates maturity of  Highbar`s  delivery 
capabilities.

In  order  to  serve  the  infrastructure  industry  in  Middle  East  more 
effectively,  Highbar  Technologies Ltd, has incorporated a  subsidiary  in 
Dubai,  named `Highbar Technologies FZ-LLC` which is now fully  operational 
and has bagged customers in Middle East.

Highbar  Technologies has developed a very strong strategic  alliance  with 
SAP  who  considers  Highbar  as a  preferred  partner  for  infrastructure 
industry.  Gartner, the world`s leading IT research and  advisory  Company, 
has published case study on managing successful IT spin-off with Highbar as 
an example. After a long time they could locate a successful spin-off worth 
writing a case study on.

Highbar continues to compete consistently with more established players  in 
the  IT industry. It has already created a niche for itself in  the  market 
and  is  a leading player that is helping grow the `IT  for  infrastructure 
market`.

Highbar  Technologies has strategically entered into a tie-up with  SAP  to 
launch Highbar CloudConnect, which offers 1st of its kind SAP ERP  solution 
for infrastructure, real estate and ready mix concrete industry on pay-per-
user-per-month  basis.  This  has provided SMEs a level  playing  field  by 
getting  access to world-class IT solutions and industry best practices  in 
an investment friendly model. The cloud based offerings have helped Highbar 
Technologies to penetrate the industry further to next level by reaching to 
the masses.

With  industry  knowledge, Highbar has  developed  infrastructure  industry 
templates  based  on the best practices of infrastructure  industry.  These 
provide  the  customers access to best practice level of  business  process 
enabled  by IT. This also reduces mindshare and timeshare of the  customer, 
while  reducing the implementation time and TCO. The Company has  developed 
Highbar  RapidStart  and  Highbar  CloudConnect  solutions  based  on   the 
templatised  approach  which  are Intellectual  Property  (IP)  assets  for 
Highbar Technologies.

Highbar  continues  to  support HCC in its IT usage.  SAP  ERP  is  already 
institutionalized in HCC`s Engineering and Construction division as well as 
in group companies and subsidiaries including HCC Infrastructure, HCC  Real 
Estate and Lavasa Corporation. All the IT applications are supported at the 
back  end by a rugged and scalable IT infrastructure  comprising  state-of-
the-art  wide area network and a well connected data centre. The Web  based 
Vendor  portal built on SAP Platform also continues to be used  effectively 
by  suppliers,  sub-contractors,  transporters  and  service  providers  to 
collaborate  and  transact  with  HCC on a  daily  basis.  To  bring  about 
operational  efficiency  and cost control, the SAP ERP system  was  further 
enhanced  by building up a host of business process  controls,  automations 
and  system  based pre-alerts and MIS reporting. The budgeting  system  for 
project sites was further enhanced to bring about simplicity in preparation 
and  ease  of  review. SAP Business Objects was  implemented  in  2011  and 
management  dashboards covering organizational level key financial  metrics 
have been implemented.

In  January 2011, SAP CRM was implemented with a view to achieve  a  better 
hit ratio, increased market share and better profit margins. Over the  last 
year  the usage of the system has stabilized and the desired benefits  have 
started to fructify. HCC`s SAP CRM implementation was the first for  Indian 
Construction  Industry and the effective implementation and  usage,  helped 
HCC win the SAP ACE award for 2011.

Highbar Technologies is on the course towards achieving its vision of being 
considered  `the  most preferred end to end IT solution provider`  for  the 
infrastructure industry.

Pillars of Support

The  operations  of  the different divisions are  supported  by  Management 
Systems, Intellectual Property Rights, Branding and Human Resource.

Management Systems

HCC`s  business  operations extend to remote project  sites  spread  across 
different  states.  Creating,  developing and  establishing  best-in  class 
processes  and  systems across these sites are fundamental  to  ensure  the 
Company`s competitive strength.

HCC has adopted an integrated approach towards Quality, Environment, Health 
and Safety and has incorporated these in business practices. The  objective 
of  an  Integrated  Management System (IMS) is to inculcate  a  culture  of 
continuous  improvement  that  will enhance quality  of  the  products  and 
maintain the highest standards of environment protection and safety of  the 
project team and workforce to maximize customer satisfaction.

This  adheres to the stringent standards stipulated by ISO 9001 : 2008  for 
Quality;  ISO 14001 : 2004 for Environment; and BS OHSAS 18001 :  2007  for 
Occupational Health and Safety.

On  the safety front, HCC focuses on creating a culture  that  continuously 
reduces the frequency of incidents to achieve the goal of `Zero  Reportable 
Injuries`.  The  Company  is  also committed  to  reducing  the  impact  on 
environment  during execution or construction of projects  by  continuously 
monitoring the environment.

HCC  has  a  good safety performance record in nine  projects,  which  have 
achieved  more than 3 million safe man-hours and five projects  which  have 
achieved 2 million safe man-hours without any reportable accident until

March 2012.

To  achieve  these objectives, engineers at various functional  levels  are 
trained  by professional agencies to ensure proper operation  of  processes 
and  implementations  of  systems.  These trained  engineers  then  act  as 
internal auditors to conduct regular bi-annual internal IMS audits based on 
a detailed schedule.

There were several IMS-related developments in 201112. Between November 21, 
2011 and December 23, 2011, M/s TUV NORD, the certifying agency,  conducted 
a  surveillance  audit for ISO 14001: 2004, BS OHSAS 18001:  2007  and  ISO 
9001: 2008 to verify the status of compliance to the requirements of  these 
standards. The objective and effectiveness of Integrated Management  System 
has  been  verified  during this audit course. Five project  sites  of  the 
Company  and  most of the functions at corporate office were  subjected  to 
these  audits. The auditors recommended continuation of  certification  for 
ISO 14001: 2004, BS OHSAS 18001: 2007 and ISO 9001: 2008 valid up to  March 
2014.

Intellectual Property Rights

HCC  continued  to  pursue its initiative on  creation  and  protection  of 
Intellectual Property (IP) during 2011-12.

Patents

HCC  is  awaiting  registration on  the  following  invention  applications 
submitted to the patenting authority under the Patents Act, 1970 in  India. 
These inventions are under examination by the Patent Office:

* Pipe joint leak-testing device.

*  A  system for automatic accounting of fluids in a vessel,  container  or 
tank.

* New capping system for testing concrete and rock cores.

*  System  and  method  for  online  monitoring  of  fuel  consumption   in 
automobiles.

* System and method for detecting trespassing below a parked vehicle.

*  Geotextile Sand Container Mattresses (GSCM) lining for  temporary  river 
bed diversion channels.

Trade Marks

During   the  year  under  review,  the  Company  filed  applications   for 
registration of trade marks/obtained registration as per details below:

* In June 2011, in respect of wholly owned subsidiary, Highbar Technologies 
Limited,  obtained  registration  for the trade  mark  "Highbar"  from  the 
Registrar of Trade Marks, Mumbai.

* In July 2011, filed a multi class trade mark application for registration 
of mark `HCC Innovention ` before the Trade Marks Office, Mumbai.

*  In  January  2012,  in  respect  of  wholly  owned  subsidiary,  Highbar 
Technologies  Limited,  filed  three trade mark  applications  including  a 
multi-class application for registration of marks `Highbar Rapidstart`  and 
`Highbar Cloudconnect` before the Trade Marks Office, Mumbai.

Copyrights

*   In  October  2011,  in respect  of  wholly  owned  subsidiary,  Highbar 
Technologies  Limited,  filed two copyright registration  applications  for 
protection of `Highbar` labels (artistic work) at the Copyright Office, New 
Delhi.

Branding at HCC

HCC  continued  to  build  its brand  presence  and  communicate  its  core 
competence.  Among the major milestones achieved during the financial  year 
were the completion of the 12 Km long Marol-Maroshi water supply tunnel  in 
Mumbai as well as the 21 Km Pir Panjal Tunnel packages in Jammu & Kashmir - 
which  includes  India`s longest tunnel poised to bring  broad  gauge  rail 
connectivity to Srinagar. A structured communication programme resulted  in 
good visibility for HCC in national media, creating a connect with  India`s 
critical infrastructure projects thus enhancing perception of the HCC brand 
centred around its core philosophy of `Responsible Infrastructure`.

As India transforms the road travel experience for motorists and goods with 
the  development of several arterial national highways, HCC`s  contribution 
to  building more than 3,100 lane kms of the national highway programme  is 
increasingly  visible. Its brand presence penetrated further into  interior 
towns  when the four lane Dhule-Palesnar Tollway on NH-3, developed by  HCC 
Concessions  Ltd  in a joint venture, was opened to motorists a  full  four 
months  ahead  of  schedule.  Branding along the entire  89  Km  route  was 
specially created to guide and facilitate traffic for a safer and  smoother 
journey.  A  similar exercise was conducted along  the  Lucknow-Muzaffarpur 
Highway  on NH28 linking Lucknow and Gorakhpur and is also  underway  along 
the 276 km long NH-34 redevelopment project in West Bengal.

The  visit  of  the  Prime  Minister  of  Bhutan,  Mr.  Jigme  Y.  Thinley, 
accompanied  by  other  dignitaries from the Government of  Bhutan  to  the 
Punatsangchhu Hydel project drew attention to HCC`s continuing and key role 
in building hydel power capacities for the region.

HCC`s  website  underwent a comprehensive overhaul for enhanced  access  to 
updates,   news  and  information.  HCC`s  brand  communication   programme 
continues to be refined with the appointment and induction of project Brand 
Champions  aimed at strengthening their key role in dissemination of  brand 
values amongst all Company staff.

Internally,  key  accomplishments  across  HCC  in  the  areas  of  project 
milestones,  R&D  and  innovation were communicated  through  the  employee 
magazine HCC News and several other electronic newsletters.

Human Resources (HR)

During   the   year  2011-12,  the  focus  of  the  organisation   was   on 
consolidation,  improvement  and  reorganisation  to  meet  the  prevailing 
challenges.

Within  HR,  the  first  step  towards this  was  the  realignment  of  the 
organisation  structure  along the functional line  to  reinforce  enhanced 
focus  and accountability in various areas of business  including  business 
acquisition,  business implementation and technology. Teams were  regrouped 
and  put in place for working along the lines of the  revised  organisation 
structure.

There  were also significant initiatives in reducing costs. There has  been 
manpower  right  sizing at the sites as well as the  corporate  office.  In 
addition,  concerted  effort was put in place for  reducing  administrative 
costs right across the organisation.

While  there  was  an  emphasis  on  the  cost  side,  talent   acquisition 
initiatives  were  also carried out to fill up specific  senior  positions, 
which  were  functional  necessities  arising  out  of  the  new   business 
orientation.

Initiatives undertaken earlier to improve the human resources effectiveness 
through  automation  of  HR  systems and  processes  continued.  An  online 
Employee Portal has been developed in expediting various HR processes as  a 
self  service  model. Implementation of the manpower  deployment  tool  has 
started  delivering  results in effectively managing  the  human  resources 
inventory and the vacancies.

Financial Review

Table 1 gives the Abridged Profit and Loss Account for HCC, as a standalone 
Company, while Table 2 lists the key financial ratios.

Table 1: Abridged Profit and Loss account of HCC               (Rs. crore)
                                                     2011-12       2010-11

Revenue

Income from operations                               4,002.8       4,144.0
Less: Income from JVs                                   11.3          50.8
Net income from operations (a)                       3,991.5       4,093.2
Profit/(Loss) on integrated JVs (b)                    (3.2)         (2.5)
Total (a) + (b)                                      3,988.2       4,090.7

Expenditure

Construction expenses                                2,965.7       2,890.2
Staff costs                                            439.2         467.6
Other expenditure                                      143.5         192.0
Interest                                               543.2         329.0
Depreciation                                           162.1         152.7

Total                                                4,253.7       4,031.5

PBDIT (Including Profit/Loss on
integrated JV)

PBT (including profit/loss on                        (265.5)          59.2
integrated JV) 

Exceptional items                                    (166.3)             -

Other income                                           122.8          43.9

Exchange Gain/(Loss)                                   (9.5)           8.6

PBT (including other income, Exceptional 
items and profit/loss on                             (318.5)         111.7
integrated JVs) 

Deferred Tax Charge/(Credit)                          (96.2)          40.7

PAT                                                  (222.3)          71.0

Table 2: Key Financial Ratios

PBDIT/Net Income                                       11.0%         13.2%
PBT/Net Income                                         -8.0%          2.7%
PAT/Net Income                                         -5.6%          1.7%
ROCE                                                    4.0%          9.3%
Basic EPS (Rs.)                                       (3.66)          1.17

Internal controls and their adequacy

HCC has an adequate system of internal control to ensure that the resources 
of  the  Company  are  used efficiently and  effectively,  all  assets  are 
safeguarded and protected against loss from unauthorized use or disposition 
and  the  transactions  are authorised, recorded  and  reported  correctly, 
financial  and other data are reliable for preparing financial  information 
and  other data and for maintaining accountability of assets. The  internal 
control  is supplemented by extensive programme of internal audits,  review 
by management, documented policies, guidelines and procedures.

Cautionary Statement

Statements  in  this  Management Discussion  and  Analysis  describing  the 
Company`s  objectives,  projections,  estimates  and  expectations  may  be 
`forward  looking  statements` within the meaning of  applicable  laws  and 
regulations.  Actual results might differ substantially or materially  from 
those  expressed or implied. Important developments that could  affect  the 
Company`s  operations  include a downtrend in  the  infrastructure  sector, 
significant  changes  in  political  and  economic  environment  in  India, 
exchange  rate  fluctuations, tax laws, litigation,  labour  relations  and 
interest costs.

Corporate Social Responsibility (CSR): 

Responsible Infrastructure

Since  its  inception,  HCC has a long-standing  commitment  to  developing 
responsible infrastructure. The Company remains steadfast on its  objective 
of pursuing holistic growth with responsibility towards the people and  the 
environment. As a pioneer and trend-setter in the construction industry  in 
India,  HCC is aware of the responsibilities that accompany its  leadership 
status.  The Company has a slew of social initiatives that complements  its 
world  class operational processes and systems to provide  for  responsible 
infrastructure development.

Sustainable Practices

HCC`s  businesses  practices ensure minimal  environmental  impact  through 
appropriate water, air and waste management. This helps in optimisation  of 
resources and the quantification of such practices is disclosed through the 
annual sustainability report that uses the GRI framework of reporting. Each 
project   site  has  a  trained  sustainability  champion   for   effective 
communication.

In  2011-12 too, HCC`s Sustainability Reports have been accredited  by  the 
Global Reporting Initiative (GRI) with Application Level Check A+.

HCC  is  an organizational stakeholder of the Global  Reporting  Initiative 
(GRI)  and  a member of the GRI`s Working group on  construction  and  real 
estate sector (CRESS) tasked with developing sector specific sustainability 
reporting  guidance.  The  Company is also a member of  UN  Global  Compact 
(UNGC),  TERI  -  World Business Council  on  Sustainable  Development  and 
signatory  to various UNGC initiatives including "Caring for  Climate"  and 
"The CEO Water Mandate"

Education

HCC  regularly  trains  engineers  and other  personnel  for  its  in-house 
requirements.  Walchand  College of Engineering (WCE), one  of  the  oldest 
engineering  colleges in India, started by the Walchand family is  mentored 
by Mr. Ajit Gulabchand, Chairman & Managing Director of HCC, who serves  as 
the  Chairman of the College Board. This prestigious  academic  institution 
received  autonomy  in  2007, and in May 2011, the first  batch  of  B.Tech 
students graduated. In all, 468 engineers passed out of WCE in the academic 
year 2010-11, including 20 medalists.

HIV/AIDS

Recognizing  the serious impact that HIV/AIDS has amongst  migrant  workers 
and  in turn on the enterprise, HCC has formulated the  HIV/AIDS  Workplace 
Policy and adopted a Workplace Intervention Programme (WPI) that focuses on 
prevention  programmes and zero tolerance of stigma and  discrimination  at 
the  workplace. The WPI focuses on enhancing awareness and education  about 
HIV/AIDS,  creating  a  supportive and safe  environment  for  workers  and 
preventing  discrimination. In this endeavor, the Company is  partnered  by 
the  International  Labour  Organisation (ILO), the  Avert  Society  (USAID 
Programme) and the Clinton Global Initiative. The programme aims to sustain 
optimal  workplace  productivity by conducting  prevention,  education  and 
awareness  training.  The  WPI model is based on  three  tier  system  viz. 
Training of Trainers, Creating trained Peer Educators and Sensitization  of 
Management  (Officers), so that their support to the  programme  percolates 
down to all beneficiaries.

World  AIDS  Day on 1st December was observed across the  Company  to  show 
solidarity  and commitment to work towards the prevention of the  epidemic. 
Activities organized across project sites include screening of  informative 
movies, street plays, distribution of literature, blood donation camps  and 
various competitions.

At  the  end of 2011-12, a total of 46,398 officers and workers  have  been 
covered  through  the  WPI program. We have created a pool  of  301  Master 
Trainers  and Peer Educators across our project sites. The total number  of 
man-hours  spent  on the WPI program is now 143,674 hours.  Creation  of  a 
trained  Master  Trainer and Peer Educator pool has helped us  fulfill  our 
employee sensitization and training in-house without the need of an outside 
consultant.

During 2011-12, there were some new alliances established to further extend 
the  initiative  focusing  on  HIV/ AIDS among  women  and  children.  This 
included  HCC and the Times Foundation, in association with  the  Municipal 
Corporation of Greater Mumbai (MCGM), launching a health initiative  titled 
Project `Sahyog`. The aim of the project was to complement the Government`s 
efforts  to  increase  the  demand among  the  urban  slums  for  accessing 
affordable health care services provided by the BMC health department.  The 
programme  was  to  sensitize  workers  to  mother  and  child  health  and 
prevention  of  parent-to-child  HIV transmission  (PPTCT).  500  frontline 
workers  were trained through customized module and communication  material 
reaching to 5 lakh population of the `L` and `M` wards of Mumbai.

Water

HCC  recognizes  the  correlation of  business  sustainability  with  water 
resource management and is committed to monitor and conserve the amount  of 
water used across its construction project sites.

HCC,  the first Indian Company to endorse United Nations  Global  Compact`s 
"The CEO Water Mandate" and an Industry partner of the World Economic Forum 
(WEF),  makes  it  a  point to embed  the  principles  of  water  resources 
management  in all its activities. As a responsible corporate steward,  HCC 
has  always  been motivating other companies, to join  this  initiative  by 
presenting  best  practices of water stewardship at HCC in  various  local, 
regional, national, and international conferences and symposia. Such  moves 
are  crucial  in bringing about inclusive development for  the  nation,  in 
general, and in developing sustainable infrastructure, in particular.

To effectively implement the CEO Water Mandate, a team of water experts and 
practitioners  based at HCC`s Head Office in Mumbai, communicate  with  the 
project sites through a nodal officer ("Water Champion") stationed at  each 
site.  Over the years of implementing the CEO Water Mandate at the  project 
sites,  HCC  has  been able to optimize consumption  of  water  leading  to 
enhancement of HCC`s ability to conserve precious freshwater. It also helps 
minimize  carbon  footprint for resourcing and pumping  freshwater  to  the 
construction site. There have been a number of water interventions taken at 
projects sites of HCC spread over India and abroad.

Rain  water  harvesting,  for example, has been in practice  in  India  and 
elsewhere  from times immemorial. However, the concept of  harnessing  this 
technique  to  harvest rainwater collected  through  specifically  designed 
storm  water  drains  alongside an  infrastructure  project  like  Badarpur 
elevated  highway is unique and exemplary. This innovative  application  of 
rainwater   harvesting  technique  has  the  potential  to  recognize   the 
significance of ground water recharge of rainwater from paved surfaces  and 
demonstrates  a way to offset the impact of ever increasing paved  surfaces 
being  built in the process of infrastructure development, in general,  and 
Roads, highways, and Elevated Highways, in particular.

Similarly,  in  case  of  Vizag  Cavern  Project  (VCP),  installation   of 
sedimentation  tank(s) for solids removal at construction site was  one  of 
the regulatory compliance to be adhered to. However, producing water from a 
specifically designed effluent treatment plant for process consumption  was 
a unique HCC initiative. Adoption of Desalination Plant at the DGNP site in 
Mumbai  is  yet another innovative initiative under the aegis of  UN  Water 
Mandate. In this case, water is being sourced from the Arabian sea, treated 
through  the  desalination plant and the treated water is  being  used  for 
HCC`s process consumption.

Cumulatively,  across  all  HCC`s  projects sites  in  this  FY  2011-2012, 
approximately 285 million litres of fresh water have been conserved.

With  these  activities  and continual engagement  with  work  streams  and 
programmes of United Nations (UN), Global Reporting Initiative (GRI), World 
Economic  Forum (WEF), The Energy and Resources Institute (TERI);  HCC  has 
been translating its experiences into advocacy.

Disaster Management

HCC`s  vision is "to build on the core strengths and existing  capacity  of 
the  organization  i.e. Engineering, Project  Management  Capabilities  and 
availability of relevant resources & be well equipped to handle emergencies 
through  trained  engineers & workers, heavy equipments  and  communication 
hardware needed for disaster response, evacuation and reconstruction."

The  Company actively participates in various disaster  relief  initiatives 
and  engages  in  many National and  International  level  partnerships  to 
support disaster management.

HCC,  one  of the founding members of Disaster Resource  Partnership  (DRP) 
Global,  is  leading  the DRN National Network in India. DRP  is  a  model, 
created  by WEF, for coordinated private sector partnership in response  to 
natural  disasters. DRN India is one of the three national  networks  under 
DRP, other two being Mexico and Indonesia Network. Our Chairman &  Managing 
Director,  Mr. Ajit Gulabchand is one of the steering board members of  DRP 
Global and chairs the DRN India Network.

The  DRN  India, established in 2002, is a consortium  of  engineering  and 
construction  (E&C) companies operating in India, that seeks to  apply  the 
core skills and assets within the Company, to disaster response. DRN  India 
mainly focuses on: [1] capacity building trainings-First Responder Training 
and  Engineering  in  Emergencies to respond to  emergency  situations  [2] 
support for disaster relief operations.

Under DRN India, HCC has supported many rescue and relief operations in the 
past  ten years at National and International levels like  Tsunami  (2004), 
J&K Earthquakes (2005), Mumbai Floods (2005), Bangladesh Cyclone(2007), Leh 
Flash Floods (2010),Sikkim Earthquake (2011) etc.

Some highlights of 2011-12

* First Responder Training, a basic training given to all employees on life 
saving skills, till medical help is provided.

*  Engineering  in Emergencies Training is an  advanced  level  residential 
training  given to a subset of HCC engineers to qualify them for  emergency 
relief and rehabilitation work.

At the end of the year 2010-11, a total of 11500 employees trained In first 
responder training contributing 46000 man hours and 66 engineers trained in 
engineering in emergencies training contributing 3696 man hours.

* HCC team lead by EE trained engineers supported relief and rehabilitation 
during  Leh  Flash Floods 2010, West Bengal Train Accident  2011and  Sikkim 
earthquake 2011.

*  Several  companies including L&T, Essar, Shapoorji &  Pallonji,  Afcons, 
Halcrow, CH2MHILL, Arup, and Hirco have joined hands to take the DRN  India 
Network forward.

*  HCC  has  joined United Nation`s  International  Strategy  for  Disaster 
Reduction(UNISDR)`s  new division, Disaster Risk Reduction  Private  Sector 
Partnership (DRR-PSP) to engage the private sector in future

Disaster Risk Reduction (DRR) initiatives. Our CMD, Mr. Ajit Gulabchand  is 
a  member  of Private Sector Advisory Group along with 14 more  CEO`s  from 
leading global companies.

Community Development Initiatives

HCC has a long tradition of contributing to and investing in communities in 
and  around  its  project  sites. Under the  broad  umbrella  of  community 
development,  several  initiatives  have  made  a  lasting  impact  on  the 
economic, environmental and social conditions of local people.

Community Development Activities

* Donation of computers and other equipment to schools

* Tree plantation

* Construction of composting facilities

* Construction of roads, sanitation facilities and temples

* Provision of electricity

* Construction of irrigation and drinking water systems

* Provision of employment

* Sponsorship of vocational training programs

Other  than  this,  the project sites  also  undertake  specific  community 
development  initiatives based on HCC`s CSR mandates in  Education,  Water, 
Disaster Management and HIV/AIDS awareness.

Corporate Partnership Kihim, Maharashtra

HCC  has  partnered  with Kihim Gram Panchayat over the  past  three  years 
promoting  effective Solid Waste Management, among other environmental  and 
developmental  issues.  Last  year,  in response to  the  lack  of  garbage 
collection  facility  in the village, we handed over a  scientific  garbage 
collection van to the village Sarpanch. The van was purchased on the  basis 
of a public private partnership between HCC and the village Gram Panchayat. 
A  beach  cleaning  drive  organized by HCC at  Kihim  which  was  a  major 
community  activity.  The main objective of this program was to  clean  the 
beach  through community participation and engage students and  the  youth. 
HCC  has also donated computers to local schools with the aim of  educating 
the  students  on  various aspects of health and  environment  through  the 
medium of information technology.

Gulabchand Foundation

The Gulabchand Foundation primarily focuses on carrying out various  health 
care  and  educational initiatives for the advancement  of  underprivileged 
rural and urban sections of the society. It is a non profit making  Company 
duly  registered  in the year 2003 under Section 25 of the  Companies  Act, 
1956,  under  the  leadership of Mr Ajit Gulabchand,  Chairman  &  Managing 
Director of Hindustan Construction Company Ltd (HCC). In the past year,  GF 
has  supported,  amongst other causes, Cochlear Implant  (CI)  surgery  for 
children.  This is a surgical procedure to implant a digital device  within 
the  ear to treat profound deafness; this surgery being most  effective  in 
children.  GF provides financial support to persons for this surgery  based 
on  several factors like the recommendation of doctor, age of the  patient, 
financial  status  of  the parents,  parent`s  commitment  etc  established 
through home visit, interview with parents etc. In 2011-12, more than   Rs. 
10 Lakhs was donated for two CI surgeries on three year old girls.

During  the year under review, GF has also donated approx.  Rs. 2.49  crore 
towards  educational  activities like providing support to  students  below 
poverty  line by donating IXth and Xth std. text books to three schools  in 
Pune and for providing scholarship to needy bright students. In its aim  to 
strengthen support to educational institutions, GF has contributed  towards 
the  building  of  infrastructure  at Christel school  in  LAVASA  and  for 
development  of  international  curriculum  for  engineering  students   at 
Walchand  College of Engineering, Sangli which would enable students to  be 
creative and aspire for an innovative thinking in the field of construction 
and thereby set a new trend while serving the industry at large. Other than 
health and educational support, GF has also extended its help for the cause 
of `Save Animals` by sponsoring an education and awareness event.
 
Fetching Data...